The quick, correct way to calculate how many bricks a wall needs is: work out the actual brickwork area (length × height, minus door and window openings, columns, beams and lintels), multiply by the number of bricks per square metre for that brick and wall thickness, then add about 3–5% for waste. With 220 × 105 × 60 mm bricks and a 10 mm mortar joint, a 110 mm wall (called a "10 wall" on Vietnamese sites) needs about 62 bricks/m², and a 220 mm wall (a "20 wall") about 124 bricks/m². This lesson is written the way a master builder coaches an apprentice: from the formula and a table by brick type to a worked example taking off bricks, mortar, cement and sand for two walls with openings, with figures that add up to the last brick.
By the end of this lesson, you will be able to:
- Derive the bricks-per-m² figure for any brick from its size and the mortar joint thickness.
- Measure and calculate the actual brickwork area, correctly deducting openings, lintels, columns and beams.
- Choose a sensible waste allowance and round the order quantity.
- Estimate the mortar, cement and sand that go with the bricks and build a materials cost table that adds up.
- Avoid 5 common mistakes that leave you short of bricks halfway through or with a whole truckload left over.
Learning masonry to take on your own jobs? Quantity take-off is step 8 of the roadmap, after scaffold safety, building materials, mixing mortar, bricklaying and plastering, and house repairs. See the 8-step mason roadmap to learn in the right order.
The formula for bricks per square metre of wall
On the face of a wall, each brick occupies a cell made up of the brick itself plus one vertical (perpend) joint and one horizontal (bed) joint. Know the area of one cell and you know how many cells fit in 1 m², which is the number of bricks in one leaf.
The basic formula
Bricks per m² = 1 ÷ [(brick length + joint) × (brick height + joint)] × number of brick leaves across the wall thickness. Convert everything to metres. A normal mortar joint is about 10 mm, with an allowed range of roughly 8–12 mm.
- 220 × 105 × 60 mm brick, 10 mm joint: cell = (0.22 + 0.01) × (0.06 + 0.01) = 0.23 × 0.07 = 0.0161 m².
- Bricks per leaf: 1 ÷ 0.0161 ≈ 62.1 bricks/m².
- 110 mm wall (one 105 mm leaf): about 62 bricks/m².
- 220 mm wall (two 105 mm leaves + a 10 mm joint between): 62.1 × 2 ≈ 124 bricks/m².
Why Vietnamese builders say "10 wall" and "20 wall"
A wall built with 220 × 105 × 60 bricks is 110 mm or 220 mm thick; with about 15 mm of plaster on each face it becomes roughly 14 cm or 25 cm. On site, builders shorten these to "tuong 10" and "tuong 20" (or 11 and 22). When you read a drawing, check whether the figure is the brickwork thickness or the finished thickness, so you do not multiply by the wrong number of leaves.
Thicker joints mean fewer bricks
Try again with a 12 mm joint: 0.232 × 0.072 = 0.0167 m², and 1 ÷ 0.0167 ≈ 60 bricks/m². Just 2 mm more joint changes the count by about 2 bricks per square metre, or about 200 bricks over 100 m² of wall. So ask the crew how thick they lay their joints before you fix the quantity, and measure a few bricks from the actual batch (Figure 1) rather than trusting the size on the quotation.
Photo: Dmitry Makeev / Wikimedia Commons, CC BY-SA 4.0
Bricks per m² for common brick types
Bricks in Vietnam vary by region: the North mostly uses solid and two-hole bricks of 220 × 105 × 60 mm, the South uses four-hole hollow bricks and solid "the" bricks of 80 × 80 × 180 and 40 × 80 × 180 mm, and new buildings increasingly use unfired concrete blocks. Real bricks from each kiln and batch can differ by a few millimetres from the nominal size.
| Brick type | Size (mm) | How laid | Bricks/m² (theoretical, 10 mm joint) |
|---|---|---|---|
| Solid or two-hole brick | 220 × 105 × 60 | 110 mm wall ("10 wall") | About 62 |
| Solid or two-hole brick | 220 × 105 × 60 | 220 mm wall ("20 wall") | About 124 |
| Four-hole hollow brick | 80 × 80 × 180 | 100 mm finished wall (one leaf) | About 58.5 |
| Four-hole hollow brick | 80 × 80 × 180 | 200 mm finished wall (two leaves) | About 117 |
| Solid "the" brick | 40 × 80 × 180 | Laid flat, 100 mm finished wall | About 105 |
| Concrete block | 390 × 190 × 190 | 200 mm wall | About 12.5 |
To check any row: an 80 × 80 × 180 hollow brick laid flat shows a 180 × 80 face, so the cell is 0.19 × 0.09 = 0.0171 m² and 1 ÷ 0.0171 ≈ 58.5 bricks/m². These are theoretical figures with no waste. When a cost estimate is prepared from design documents, estimators use the current official material norms (per m³ of wall, with waste included); on site, builders often work per m² as in this lesson to order bricks quickly.
Photo: Tuong Lam Photos / Wikimedia Commons, CC0
Blocks and unfired bricks
Large blocks give a small count per m², but each one is heavier and costs more. Some unfired and lightweight concrete blocks are laid with thin-bed mortar or special adhesive with joints of just a few millimetres; in that case put the real joint thickness into the formula instead of 10 mm.
Measuring the actual brickwork area
The biggest errors in brick counts come from the area, not the formula. Beginners tend to take the length between grid lines on the drawing, multiply by the storey height, and forget to deduct the parts that are not brick.
Measuring length and height
- Length: measure the clear distance between column faces or between the faces of perpendicular walls, not the grid-line distance (Figure 3). For a wall running past several columns, add up each section between columns.
- Height: from the floor (or ground beam) to the underside of the beam or slab above, not the storey height to the top of the next floor.
- For a wall up to a sloping roof, split it into a rectangle and a triangle, calculate each and add them.
Photo: Regy05 / Wikimedia Commons, CC BY-SA 4.0
What to deduct
- Door, window and vent openings: deduct the size of the opening left in the wall, not the size of the door leaf.
- Lintels: the small concrete beam over an opening, usually about 20 cm longer than the opening on each side (check the drawing). The lintel is not brick, so deduct it.
- Concrete columns, piers, beams and wall ties within the wall face: deduct them.
- Small holes (service boxes under about 0.1 m²) are usually not deducted, because the cut bricks are wasted anyway.
What to add
Brick piers, ledges, brick window sills, gable walls, brick entrance steps, built-in kitchen counters: calculate each separately by volume or by counting bricks, then add them to the total. Do not wait until you are building the steps to find you have run out.
Waste, rounding and ordering
Bricks break during unloading, warped ones get rejected, and half bricks are cut at wall ends and around openings. The theoretical count includes none of that.
Choosing a waste allowance
| Situation | Waste to add (reference) |
|---|---|
| Long walls, few openings, good bricks, truck unloads right at the site | About 3% |
| Ordinary house, many openings and corners | About 5% |
| Bricks moved several times, poor batch, lots of cut detail | About 7–10% |
Waste above 10% usually points to problems with handling and storage, not with the calculation. After adding waste, round up to the way the supplier sells (by the hundred, by the truck, by the pallet).
Order one batch and store it properly
Bricks from two batches may differ in size, and mixing them in one wall makes even joints hard. Order enough for the whole item at once, or state clearly that you need the same kiln and batch. Stack delivered bricks neatly on flat, dry ground near the mortar mixing area, covered from rain (Figure 4); fired clay bricks should be wetted before laying as specified, so they do not suck the water out of the mortar.
Photo: 松岡明芳 / Wikimedia Commons, CC BY-SA 4.0
Counting on delivery
Count one sample stack (rows × bricks per row) and multiply by the number of stacks. Bricks tipped in a heap are hard to count; agree with the seller to stack them or count by pallet. Pick 10 bricks at random, measure their length, tap them to listen, and look for cracks; if many are defective, tell the seller at delivery.
Mortar, cement and sand to go with the bricks
Ordering bricks but forgetting mortar still stops the job. This section gives a quick estimate for ordering; for a formal estimate, use the mortar mix in the current norms with the actual cement and sand.
Mortar per m² of wall
The theoretical joint volume of a wall in 220 × 105 × 60 bricks is about 18–22% of the wall volume. Adding dropped mortar and mortar lost into the brick holes, in practice you typically use about 0.023–0.03 m³ of mortar per m² of 110 mm wall and 0.05–0.065 m³ per m² of 220 mm wall (reference, depending on skill and brick type). For bricks with many holes and thick joints, use the upper end.
Cement and sand for the mortar
House walls are usually laid in mortar grade 50 or 75 as designed (Vietnamese grades, roughly 5 and 7.5 MPa). For a quick estimate, 1 m³ of grade 75 mortar needs about 230–300 kg of cement and about 1.1 m³ of sand, depending on the cement type and the fineness and moisture of the sand. Mixing and batching on site belong to step 3 of the roadmap; the lesson Grade 250 concrete mix ratio: per cubic metre, per bag, per bucket shows bucket batching that also works for mortar.
Safety when handling bricks and cement
Safety warning: A solid brick weighs about 2–2.5 kg and a small stack already weighs tens of kilograms: lift with your legs, keep your back straight and wear gloves against scrapes. Never pile bricks in one spot on a newly cast slab, a balcony or a scaffold platform beyond its permitted load; spread them out and ask the engineer if unsure. Cement and wet mortar are alkaline and burn skin: wear gloves, boots and glasses when mixing; if mortar gets in your eyes, rinse with clean water continuously for at least 15 minutes and see a doctor. When hoisting bricks with a pulley or winch, people on the ground must stay clear of the drop zone.
Worked example: taking off bricks for two walls with openings
A townhouse in Hanoi, second floor, built with two-hole 220 × 105 × 60 mm bricks and 10 mm joints. The brickwork height from floor to beam soffit is 3.3 m. Two walls are to be built:
- Wall A (110 mm, bedroom partition): clear length 4.2 m, one door opening 0.9 × 2.2 m, lintel 1.3 m long and 0.1 m high.
- Wall B (220 mm, external wall): clear length 5.0 m, one window opening 1.4 × 1.4 m, lintel 1.8 m long and 0.1 m high.
Step 1: actual brickwork area
- Wall A: 4.2 × 3.3 = 13.86 m²; less the door 0.9 × 2.2 = 1.98 m²; less the lintel 1.3 × 0.1 = 0.13 m². Leaves 13.86 − 1.98 − 0.13 = 11.75 m².
- Wall B: 5.0 × 3.3 = 16.5 m²; less the window 1.4 × 1.4 = 1.96 m²; less the lintel 1.8 × 0.1 = 0.18 m². Leaves 16.5 − 1.96 − 0.18 = 14.36 m².
Step 2: number of bricks
- Wall A: 11.75 × 62 = 728.5, rounded to 729 bricks.
- Wall B: 14.36 × 124 = 1,780.64, rounded to 1,781 bricks.
- Total: 729 + 1,781 = 2,510 bricks. A house with many openings, so add 5%: 2,510 × 1.05 = 2,635.5, rounded to 2,636 bricks. Order 2,700 bricks as a round number.
Step 3: mortar, cement and sand
- Mortar for wall A: 11.75 × 0.025 ≈ 0.29 m³. Wall B: 14.36 × 0.055 ≈ 0.79 m³. Total 0.29 + 0.79 = 1.08 m³ of mortar.
- Cement (grade 75 mortar, taking 250 kg/m³): 1.08 × 250 = 270 kg, or 5.4 bags of 50 kg; buy 6 bags.
- Sand: 1.08 × 1.1 ≈ 1.19 m³; order 1.5 m³, because sand is lost when tipped and sieved.
Step 4: materials cost (2026 reference prices, varying by area)
| Material | Quantity × unit price | Amount |
|---|---|---|
| Two-hole brick 220 × 105 × 60 | 2,700 bricks × 1,500 VND | 4,050,000 VND |
| Cement, 50 kg bag | 6 bags × 90,000 VND | 540,000 VND |
| Building sand | 1.5 m³ × 350,000 VND | 525,000 VND |
| Total materials | 5,115,000 VND | |
Check: 4,050,000 + 540,000 + 525,000 = 5,115,000 VND (about 205 US dollars) for 11.75 + 14.36 = 26.11 m² of wall, roughly 196,000 VND per m² in materials. Brick, cement and sand prices vary widely by region and building season (bricks range from about 1,200 to 2,000 VND each in different places), so get real quotes before agreeing a price with the owner. The table excludes labour, plastering mortar and carrying materials upstairs.
Common mistakes when calculating bricks
Using grid-line length and storey height
Sign: lots of bricks left over, and the owner complains the quote is high. Cause: columns and beams counted as wall area. Fix: measure clear lengths, height to the beam soffit, and deduct columns within the wall face.
Deducting the opening but forgetting the lintel, or forgetting piers
Sign: the count is a few percent off reality, sometimes over, sometimes under. Cause: small details missed. Fix: make a table wall by wall, each row listing what is deducted and what is added, as in the example.
Using the 10-wall figure for a 20 wall
Sign: nearly half the bricks for the external walls are missing. Cause: not telling 110 and 220 walls apart on the drawing, or confusing finished thickness with brickwork thickness. Fix: colour each wall type differently on the drawing and calculate each type separately.
Forgetting waste, or adding it twice
Sign: a few hundred bricks short at the end, or a whole truckload left over. Cause: using the theoretical figure with no waste, or adding 5% on top of a norm that already includes waste. Fix: always note whether a figure is theoretical or already includes waste.
Not measuring real bricks
Sign: the first floor uses up the bricks planned for two floors. Cause: the real batch is smaller than nominal, and the crew lays thick joints. Fix: measure 10 sample bricks, ask about joint thickness, and recalculate bricks per m² before placing a large order.
Frequently asked questions
How many bricks are in 1 m² of a 110 mm wall?
With 220 × 105 × 60 mm bricks and a 10 mm joint, about 62 bricks/m² before waste, about 65 with 5% added. With 80 × 80 × 180 hollow bricks for a 100 mm wall, about 58–59 bricks/m².
How many bricks are in 1 m² of a 220 mm wall?
Twice the 110 mm wall with the same brick: about 124 bricks/m² with 220 × 105 × 60 bricks, about 130 with 5% waste.
How many bricks are in 1 m³ of wall?
Divide the bricks per m² by the wall thickness. For example, a 220 mm wall in 220 × 105 × 60 bricks: 124 ÷ 0.22 ≈ 564 bricks/m³ in theory. For formal estimates per m³, use the current norms for the specific brick and wall type.
What is a reasonable brick waste allowance?
Usually about 3–5% for an ordinary house, up to 7–10% when bricks are moved several times or the batch is poor. If waste is higher than that, check handling and storage.
Practice exercises and self-assessment
- Measure 10 real bricks on a site, find the average size, and recalculate bricks per m² for 110 and 220 mm walls with 10 mm and 12 mm joints.
- Take off bricks for a 3.6 × 4.0 m bedroom with 3.2 m brickwork height, four 110 mm walls, one 0.8 × 2.2 m door, one 1.2 × 1.4 m window, and 0.1 m high lintels extending 0.2 m beyond each side of the openings.
- Build a cost table for bricks, cement and sand following the example, using real prices where you live.
Self-assessment criteria
- Pass: the bedroom exercise gives a gross wall area of 2 × (3.6 + 4.0) × 3.2 = 48.64 m² before deducting openings and lintels, with each deduction clearly listed.
- Pass: brick count, waste, rounding and cost all add up line by line.
- Pass: you can explain why a 12 mm joint reduces the bricks per m².
- Not yet: using grid-line lengths, forgetting lintels, or not stating whether waste is included.
Quantity take-off is a skill of the final roadmap step, Skills check, quantity take-off and finding work. To revise and go further, take off the bricks before every job, record the bricks actually used when it is finished, and compare; after five or ten jobs you will have your own crew's waste factor. The next move is to also take off plaster, lintel concrete and floor screed so you can quote a complete work item yourself.