Tiling a bathroom wall properly means working in order: pipes run and pressure tested, walls rendered flat, waterproofing at the base of the walls and in the shower zone, the tiles set out on paper, walls tiled from the second row upwards off a ledger board with tile adhesive and spacers, the floor laid, and only then the bottom row of wall tiles and the grout. Hollow-sounding or falling tiles, water seeping into the next room and slivers of cut tile in plain sight nearly always come from working in the wrong order or not setting out first. This lesson is written the way a lead tiler coaches an apprentice, with a worked example of a 1.6 × 2.0 m bathroom that goes from wall area to boxes of tiles, bags of adhesive and a cost that adds up.
By the end of this lesson, you will be able to:
- Put the trades in a bathroom in the right order: plumbing, electrics, render, waterproofing, wall tiling, floor tiling, grout.
- Check the wall substrate and the waterproofing at the base of the walls before tiling, and know when to stop.
- Set out tiles vertically and horizontally so cuts end up out of sight and are never smaller than half a tile.
- Choose adhesive, trowel notch and spacers; tile row by row off a ledger board, drill holes for pipe outlets and finish inside and outside corners.
- Work out wall area, boxes of tiles, bags of adhesive and labour cost for a bathroom.
Learning tiling properly? Bathroom wall tiling is step 5 of the roadmap, after materials and cutter safety, reading drawings and setting out, substrate preparation, and floor tiling. See the 8-step tiler roadmap to learn in the right order.
The order of work in a bathroom: where does wall tiling fit?
A bathroom is where several trades share a few square metres. Get the order wrong and you end up breaking new tiles to fix a pipe, or water seeps through the joint at the base of the wall into the next room.
The usual order
- The plumber runs supply and drain pipes in the walls; the electrician runs conduit and back boxes.
- Pressure test the supply pipes before rendering (see the lesson installing hot and cold water supply pipes and pressure testing before plastering).
- Render the walls flat and screed the floor with a fall to the floor drain.
- Waterproof the floor, the base of the walls and the shower walls; flood test.
- Tile the walls from the second row up.
- Lay the floor tiles.
- Tile the bottom row of the walls, overlapping the edge of the floor tiles.
- Grout, seal corners with silicone, fit sanitaryware, clean and hand over.
Why the bottom row of wall tiles goes on last
When the bottom row is tiled last and sits on top of the floor tiles, water running down the wall lands on the face of the floor tile instead of getting into the joint between floor and wall. Tiling the bottom row last also lets you cut it to the real finished floor level, regardless of any error in the screed.
Walls first or floor first?
Some crews lay the floor first and then tile the walls so they have a clean surface for trestles. Either works as long as the wall tiles sit over the floor tiles and the finished floor is protected from knocks and dropped adhesive. This lesson follows the walls-first approach common in Vietnamese townhouses.
Preparing the wall and checking the waterproofing
Tile adhesive only bonds well to a flat, sound, clean surface. On an uneven wall the adhesive bed is thick in places and thin in others, so tiles sound hollow and edges do not line up.
Checking the wall
- Flatness: put a 2 m aluminium straightedge against the wall in several directions; for thin-bed adhesive the gap should generally not exceed about 3 mm; if it does, patch-render first.
- Plumb and square: use a plumb line or a laser; walls meeting at a corner should be close to square, otherwise the cut tiles at the corner will vary in width from bottom to top.
- Sound and clean: scratch-test for crumbling; brush off dust, render spatter, oil and grease.
- Pipe outlets: threaded outlets should stand out from the render by the thickness of tile plus adhesive, as agreed with the plumber.
Waterproofing the base of the walls and the shower zone
Common practice is to waterproof the whole floor, turn it up the walls about 20–30 cm, and cover the shower walls to about 1.8 m or higher. A typical material is a two-part polymer-modified cementitious membrane, applied in two coats at right angles with reinforcing mesh in the corners and around pipe penetrations. The tiler does not always do this work, but must check it before tiling: the membrane is continuous and not peeling, the corners have mesh, it has been flood tested (often 24–48 hours) and the floor below shows no leaks.
When to stop and not tile
The wall is still wet from rendering or from rain getting in, the membrane has not cured for the time the maker states, the water pipes have not been pressure tested, or electrical conduit runs across the shower zone without a watertight box. Note it and tell the owner; do not tile over it to keep to schedule.
Setting out bathroom wall tiles before you start
Setting out means deciding where the full tiles and the cut tiles go. A well-tiled wall seen from the door has straight rows and even joints, like the subway-tiled bathroom in Figure 1, with no slivers of cut tile where they catch the eye.
Photo: Alf van Beem / Wikimedia Commons, CC0
Setting out vertically
- Mark a datum level (usually +1.0 m above finished floor level) with a laser or water level and snap a chalk line around the room.
- Count up from the finished floor: the bottom row is a full tile, the following rows are full tiles, and the cut row goes at the top against the ceiling (often partly hidden by a plasterboard ceiling or cornice).
- If the top row would be a strip under half a tile, drop the whole layout so the bottom and top rows are both cut, each at least half a tile.
- Check the heights of shower, tap and socket outlets so that holes do not land right on the joint between two tiles.
Setting out horizontally
- The first wall seen from the door (usually the basin or shower wall): centre the layout so the cuts on both sides are equal.
- Secondary walls: start full tiles from the most visible corner and push cuts to the hidden corner behind the door.
- Never leave a cut smaller than half a tile; if the numbers give a narrow strip, shift the layout by half a tile.
- The basin, mirror and wall niches should sit on the centre of a tile or the centre of a joint.
Horizontal or vertical tiles?
Rectangular 30 × 60 cm tiles laid horizontally make a narrow room look wider; laid vertically they make the ceiling look higher. Subway tiles are usually laid in half-bond. Once you choose, keep the same direction throughout the room.
Choosing tile adhesive, trowel and spacers
Thick-bed sand and cement is still seen on walls, but for glazed ceramic and low-absorption porcelain tiles, thin-bed tile adhesive bonds better, weighs less and makes flatness easier to control. The comparison of adhesive and mortar is in the lesson how to lay floor tiles with adhesive; below are the points specific to walls.
| Wall tile type | Recommended adhesive | Square-notch trowel | Notes |
|---|---|---|---|
| Glazed wall tiles up to 30 × 60 cm | Standard cement-based, slip-resistant (class T) | 6–8 mm | Back-butter the tiles in the shower zone |
| Porcelain 30 × 60, 40 × 80 cm | Improved (C2), slip-resistant | 8–10 mm | Adhesive on wall and tile |
| Large format from 60 × 120 cm on walls | Improved deformable adhesive (C2TE, S1) | 10–12 mm | Always double-buttered, two people, levelling clips |
| Subway tiles, mosaic | Fine slip-resistant adhesive | 4–6 mm | Thin, even bed |
Why walls need slip-resistant adhesive
On a wall, the weight of the tile pulls it downwards before the adhesive sets. Slip-resistant adhesive (marked T on the bag) holds the tile in place on fresh adhesive, so in some places you can even tile downwards without slippage. Even so, it is still best to tile upwards from a ledger board.
Adhesive coverage in wet areas
On shower walls the back of each tile should be almost fully covered (often recommended at about 90% or more), never five dabs of adhesive. Voids behind the tile hold water that seeps through the grout, causing stains, smells and hollow tiles over time. Pull off a freshly set tile now and then to check the coverage.
Spacers and levelling clips
Wall joints are usually 1.5–3 mm depending on the tile: rectified tiles take a thin joint, non-rectified tiles a wider one. Plastic cross or T spacers keep joints even; a levelling system (clips and wedges) keeps the edges of tiles from 60 cm upwards flush with each other.
Step-by-step bathroom wall tiling
Tools: laser or water level, 2 m straightedge, spirit level, tile cutter or angle grinder, drill with diamond hole saws, notched and flat trowels, mixing paddle, rubber mallet, spacers, a ledger board (a straight aluminium or timber batten) and wall plugs.
Steps 1–3: ledger board and the first row
- Fix a straight, level ledger board with its top edge at the underside of the second row (the height of the bottom row plus one joint, measured from finished floor level).
- Mix the adhesive with the amount of water on the bag, let it stand a few minutes and remix; only mix what you can use within the maker's pot life.
- Comb adhesive onto the wall with the notched trowel in one direction, back-butter the tile thinly, set the first row resting on the board as in Figure 2, and press with a slight slide across the ridges so the adhesive flattens out.
Photo: MTA Capital Construction Mega Projects / Wikimedia Commons, CC BY 2.0
Steps 4–6: the rows above
- Put spacers at every tile corner and continue row by row upwards, spreading about 1 m² of adhesive at a time so it does not skin over.
- After each row, check flatness with the straightedge and level with the spirit level; every 2–3 rows check plumb with the laser.
- Wipe adhesive off the tile face and out of the joints while it is fresh; set adhesive in the joints leaves the grout thin and prone to cracking.
Step 7: holes for pipe outlets and tiling around fittings
Measure the centre of each outlet from the two nearest tile edges, mark it on the tile face and drill with a diamond hole saw of the right size (a few mm larger than the thread to allow adjustment). Drill from the glazed face at moderate speed, with water cooling if the bit needs it. Large holes such as for a concealed basin waste are cut out and later hidden by the fitting's cover plate. A finished wall with openings left for concealed fittings looks like Figure 3.
Photo: MTA Capital Construction Mega Projects / Wikimedia Commons, CC BY 2.0
Inside corners, outside corners, edges and the bottom row
Corners are the first thing people look at and the most common place for cracked grout, because the two walls move differently.
Inside corners
Tile the main wall first and butt the side wall tiles against it, leaving a 2–3 mm gap in the corner. Do not fill this gap with cement grout; seal it with mould-resistant silicone after grouting. Inside corners filled with rigid grout often crack vertically within a few months.
Outside corners and edges
- Corner trims (aluminium, stainless steel or PVC): bedded into the adhesive before the second tile goes on; quick and protects the glazed edge.
- 45-degree mitre: two tiles meet in a sharp corner; neat, but needs equipment and skill, and the edge chips easily if knocked.
- Half-height tiling: finish with a trim or border tile, the top edge following the laser line.
The bottom row and the floor junction
After the floor is laid, cut the bottom row to the remaining height and set it over the floor tiles, leaving a small gap above the floor tile for silicone. Never use rigid grout between wall and floor: two planes meet here and the joint must be flexible.
Safety when tiling a bathroom
A bathroom is small and dusty, with water pipes and cables buried in the walls, so the risks are more concentrated than in a living room.
Safety warning: Cutting and grinding tiles creates fine silica dust that damages the lungs over the years: cut wet or with dust extraction, wear a fine-dust mask, safety glasses and ear protection, and cut in a ventilated space outside the bathroom. Angle grinders must have their guard and the right blade; unplug before changing blades. With a wet saw, the socket must be protected by an RCD and the cable kept out of the water. Before drilling for the ledger board or holes, scan for buried pipes and cables, and switch off the breaker for any sockets and lights in the area. Cement-based tile adhesive is alkaline: wear gloves; if it splashes in the eye, rinse with clean running water for at least 15 minutes and see a doctor. Use an A-frame ladder locked open and never stand it on freshly applied, wet waterproofing.
Protecting the waterproofing
Do not stand ladders or sharp-bottomed buckets on the membrane before it has a protective layer; put down boards. Fix the ledger board above the waterproofed band at the base of the walls, and never drill through a waterproofed area.
Protecting an occupied home
Cover doors and any fitted sanitaryware with plastic sheeting, and tape over the floor drain and waste pipes so mortar and adhesive do not fall in and block them.
Worked example: a 1.6 × 2.0 m bathroom with 30 × 60 cm tiles
A townhouse bathroom of 1.6 × 2.0 m is tiled up to a plasterboard ceiling 2.7 m above finished floor level. The tiles are 30 × 60 cm porcelain, laid horizontally with 2 mm joints. There is a 0.7 × 2.1 m door and a 0.6 × 0.6 m window. The waterproofing is done and has passed its flood test.
Step 1: wall area and boxes of tiles
- Perimeter: 2 × (1.6 + 2.0) = 7.2 m. Wall area: 7.2 × 2.7 = 19.44 m².
- Minus openings: 0.7 × 2.1 = 1.47 m² and 0.6 × 0.6 = 0.36 m², total 1.83 m². Area to tile: 19.44 − 1.83 = 17.61 m².
- Add 8% cutting waste: 17.61 × 1.08 ≈ 19.02 m². A box of 8 tiles at 30 × 60 = 8 × 0.18 = 1.44 m²; 19.02 ÷ 1.44 ≈ 13.2, so buy 14 boxes (20.16 m²).
Step 2: setting out the 2.0 m shower wall
- Vertically: 8 full rows plus 8 joints = 8 × 30 + 8 × 0.2 = 241.6 cm. That leaves 270 − 241.6 = 28.4 cm, so the top row is cut to about 28 cm, nearly a full tile, against the ceiling: pass.
- Horizontally: 2 full tiles in the centre and 3 joints take 2 × 60 + 3 × 0.2 = 120.6 cm. That leaves 200 − 120.6 = 79.4 cm, split equally into a 39.7 cm cut on each side, more than half a tile (30 cm): pass, and symmetrical.
- The ledger board's top edge sits 30.2 cm above finished floor level (a 30 cm bottom row plus a 0.2 cm joint).
Step 3: materials and cost (2026 reference for Vietnam, varies by area; tiles supplied by the owner)
| Item | Quantity × unit price | Amount |
|---|---|---|
| Slip-resistant tile adhesive, 25 kg bag (about 4.5 kg/m² when double-buttered) | 4 bags × 180,000 VND | 720,000 VND |
| 2 mm spacers, levelling clips | 1 set | 150,000 VND |
| Outside corner trims | 2 lengths × 60,000 VND | 120,000 VND |
| Diamond hole saw (wear) | 1 bit | 100,000 VND |
| Mould-resistant silicone for corners | 2 tubes × 90,000 VND | 180,000 VND |
| Wall tiling labour | 17.61 m² × 180,000 VND | 3,169,800 VND |
| Total | 4,439,800 VND | |
Check: adhesive 17.61 × 4.5 ≈ 79.2 kg, and 4 bags of 25 kg = 100 kg covers waste as well. Total: 720,000 + 150,000 + 120,000 + 100,000 + 180,000 + 3,169,800 = 4,439,800 VND (about 170 USD). Wall tiling labour in Vietnam is commonly about 150,000–250,000 VND/m² depending on tile size and area; large format tiles and mitred corners usually cost extra.
Common mistakes when tiling bathroom walls
Wall tiles sound hollow or fall off after a few months
Sign: tapping sounds hollow, a tile wobbles slightly or falls. Cause: poor adhesive coverage, adhesive skinned over before the tile went on, a dusty substrate, large tiles not double-buttered. Fix: remove the hollow tile, scrape off the old adhesive and refix with fresh adhesive and full coverage.
A sliver of tile at the top
Sign: a 3–5 cm strip of tile against the ceiling. Cause: no setting out, just tiling up from the floor and seeing where it ends. Prevention: set out on paper and snap lines before fixing the ledger board.
Water seeping into the next room, damp wall base
Sign: the wall of the next room or the outside wall base gets damp stains after use. Cause: missing or damaged waterproofing at the base of the wall, cracked rigid grout at the bottom row, untreated pipe penetrations. Prevention: inspect and flood test before tiling, never drill through waterproofing, and seal the wall-floor joint with silicone.
Off-centre holes and chipped glaze
Sign: the outlet is off-centre in its hole and the glaze around it is chipped. Cause: measuring from the wall corner instead of the nearest tile edges, drilling at high speed without cooling. Fix: measure from the two tile edges and drill slowly from the glazed face.
Frequently asked questions
How high should bathroom walls be tiled?
Townhouses today are usually tiled to the ceiling for easy cleaning. At a minimum, the shower zone should be tiled to about 1.8–2.0 m; dry walls can be tiled to half height depending on the design.
Should the walls or the floor be tiled first?
Both work as long as the wall tiles sit over the floor tiles. The common way is to tile the walls from the second row up, lay the floor, then tile the bottom row.
Can new tiles go over old tiles?
Yes, if the old tiles are firmly bonded, not hollow, the wall is flat enough and you use a suitable improved adhesive; key the glaze, remove grease, and re-check pipe outlets because the wall gets thicker. If many old tiles are hollow, strip them off.
How soon can wall tiles be grouted?
Usually once the adhesive is hard enough as the bag states, commonly around 24 hours. Grouting too early can shift tiles and make the grout sink.
Practice tasks and self-assessment
- Draw the four walls of a real bathroom laid flat, set out 30 × 60 cm tiles in both directions, and mark the cuts and the pipe outlet holes.
- Tile a 1.2 × 1.5 m test panel off a ledger board with one drilled outlet hole and one outside corner with a trim.
- Work out materials and cost for a 1.8 × 2.2 m bathroom tiled to 2.8 m, following the worked example.
Self-assessment criteria
- Pass: a 2 m straightedge shows no gap over about 2 mm, and you cannot feel lippage between tiles with your hand.
- Pass: no cut smaller than half a tile where it can be seen; hole centres within 2 mm.
- Pass: a test tile pulled off shows near-full adhesive coverage; tapping the panel gives no hollow sound.
- Not yet: tiling without checking the waterproofing, rigid grout in inside corners and at the wall base, or material sums that do not add up.
Photo: MTA Capital Construction Mega Projects / Wikimedia Commons, CC BY 2.0
Once the walls are tiled, move on to the next roadmap step: Grouting, epoxy grout and cleaning for handover, as in Figure 4, where you learn to choose grout for wet areas, grout without sunken joints, seal corners with silicone and sign off with the owner.
Keep learning tiling: after wall tiling come grouting, epoxy grout, a complete bathroom project and per-m² quoting. See the 8-step tiler roadmap.