A site supervisor reads construction drawings differently from the person who drew them: you do not just understand each sheet, you read all three disciplines (architecture, structure and MEP, meaning electrical, plumbing and air conditioning) together, overlay them to find where they disagree, and send written questions to the designers before the trades start work. A 100 mm clash found on paper costs one query form; found after the concrete is poured, it means breaking out, drilling, repairs and arguments about who pays. This lesson shows how to read a townhouse drawing set in the right order, with a worked example of cross-checking three disciplines and a sample design query.
By the end of this lesson, you will be able to:
- Check that a design set is complete, current and issued "for construction" before you use it.
- Read architectural plans and sections to get grid lines, dimensions, levels, openings and clear heights.
- Read structural plans, general notes and rebar details for beams, columns and slabs using the notation common in Vietnam.
- Read electrical and plumbing drawings and find where pipes and shafts clash with beams, columns and ceilings.
- Build a table of discrepancies between disciplines and write a design query with location, references, question and proposal.
Learning site supervision properly? Reading design documents is step 2 of the roadmap, right after site safety and before checking incoming materials. See the 8-step construction site supervisor roadmap to learn in the right order.
Why a supervisor reads drawings
A supervisor reads drawings to answer three questions: which sheet do we build from, which numbers do we inspect against, and where do the sheets say different things. The third question is the supervisor's own job, because the three disciplines are usually drawn by three people at three different times.
The three disciplines in a townhouse set
- Architecture: floor plans, elevations, sections, stair, bathroom and door details, finishes schedule. Answers "how big is each room, where are the finished levels".
- Structure: general notes, foundation plan, floor framing plans, column, beam and slab details, bar schedules. Answers "where is the load-bearing frame, how big is it, what steel".
- MEP (mechanical, electrical, plumbing): power, lighting, water supply, drainage, air conditioning, ventilation, lightning protection. Answers "where do the pipes and cables run, and what do they pass through".
How this step links to the others
In step 1 you learned construction site safety, which still applies when you take drawings out on site. Line types, scales and title blocks are not repeated here: if they are new to you, read how to read architectural drawings from the architectural drafter career first. This lesson focuses on reading across disciplines.
Checking the drawing set before reading details
The most expensive mistake is reading a superseded sheet correctly. Spend 30 to 60 minutes checking the whole set first.
Complete, and matching the drawing list
Each discipline has a drawing list. Count the sheets you actually have against it and mark anything missing. A structural set without its general notes sheet has a serious gap: that sheet usually states concrete strength, steel type, concrete cover, lap lengths and the standards applied, and it is the basis for inspections later.
Right type and right revision
- Building permit drawings only show size, layout, elevations, setbacks and height so the authority can issue a permit. Do not build from them.
- Construction drawings have enough detail for the trades to build, and usually carry the client's stamp or signature as required by the project's quality rules and contract. Ask the client which set is the approved one.
- Revisions: the title block usually has a revision box with dates. If two sheets share a number but differ in revision, keep only the latest on site and cross out or collect the old one.
Keep a drawing register
A simple table of sheet number, title, revision, date received and who issued it. When a dispute comes up about "which version the crew built from", this register is your evidence. Any change from the approved design must be accepted in writing by the designer and the client under current rules; a supervisor does not redraw sheets, and does not accept "verbal changes".
Reading architectural drawings: grids, dimensions, levels
Read architecture first because it gives the overall picture.
Floor plans: start from the grid
The setting-out grid (numbered lines 1, 2, 3 one way, lettered lines A, B, C the other) is the shared backbone of all three disciplines. The first job is to add up the dimension chain between grid lines and compare it with the overall dimension, then read rooms, walls, doors and slab openings (stairs, light wells, service shafts).
Sections: levels and clear heights
Sections give the finished level of each floor (for example ±0.000 at ground floor, +3.600 at level 2), floor-to-floor height, beam soffit level, ceiling level, window sill height and balustrade height. Two numbers that are often missed: the thickness of the floor finish build-up and the clear height under beams. See Figure 2: one section shows every floor, the roof and the basement on a single sheet.
Bathroom, stair and door details
Bathroom details show how far the bathroom slab is dropped, where the floor drains sit, the fall towards them and the waterproofing layers; stair details give the number and size of steps. Both tie directly into structure and plumbing, so mark them for cross-checking.
Photo: Abdel-Moneim Mustafa / Wikimedia Commons, CC BY-SA 4.0
Reading structural drawings and rebar details
Structure cannot be fixed once the concrete is in, so read it most carefully, in this order: general notes, foundation plan, floor framing plans, then details.
Structural general notes
This sheet usually gives the concrete strength class for each element (for example B20, roughly equal to the older grade 250 used in Vietnam), the steel type (designations such as CB240-T for plain bars and CB300-V for deformed bars are common on Vietnamese drawings), concrete cover, anchorage and lap lengths as multiples of bar diameter, rules for openings and pipes through beams, and the list of applicable standards. Copy these numbers onto one page of your site notebook.
Framing plans: element names
The framing plan names every element: columns C1, C2; beams D1, D2 ("D" for "dam", the Vietnamese word for beam; some designers use DC and DP for main and secondary beams); slabs S1, S2 with thickness; footings M1, M2. Beam sizes are often written as 220 × 400, meaning 220 mm wide and 400 mm deep (usually including the slab). Check the structural slab level: it should sit below the architectural finished level by exactly the finish thickness.
Reading rebar notation on beam, column and slab sections
| Common notation | Meaning | What the supervisor checks at inspection |
|---|---|---|
| 3Ø18 | 3 bars, 18 mm diameter | Count 3 bars, right diameter, right layer (top or bottom) |
| Ø6a150 (or Ø6@150) | Ø6 bars at 150 mm spacing | Stirrup or slab bar spacing, count bars over a length |
| Ø6a100/200 | Stirrups at 100 mm near beam ends, 200 mm in the middle | Length of the closely spaced zone shown on the beam detail |
| Circled number (1, 2…) | Bar mark, looked up in the bar schedule | Bent shape, length and number of bars |
| 40d (lap note) | Lap length equal to 40 bar diameters | Ø16 laps 640 mm, Ø18 laps 720 mm |
Figure 3 is a rebar shop drawing in US units, but you read it the same way: each group of bars has a count, size, spacing and position, with a schedule of shapes below. Reading details carefully now speeds up inspection later; measuring, counting stirrups and checking laps on site are covered in rebar inspection before pouring.
Photo: Stephen Shay / Wikimedia Commons, CC BY-SA 3.0
Reading electrical, plumbing and air-conditioning drawings
MEP drawings are rarely read carefully before concrete is poured, and that is the main reason for breaking out later. Pay most attention to anything that must be cast in or left open in the structure.
Electrical drawings
- Lighting and power plans: positions and mounting heights of lights, switches and sockets.
- Distribution board schematic: number of circuits, breaker sizes, cable sizes; used later to check materials.
- Conduits cast in slabs: must be placed before the pour, so read them together with the framing plan.
Plumbing drawings
These cover water supply and drainage plans for each floor, an isometric diagram and bathroom details. Follow the water: roof tank, riser, branches to fixtures; for drainage, from floor drains and toilets through branch pipes and stacks to inspection pits and the septic tank. Horizontal drains need the fall shown on the drawing (often around 1 to 3 percent), so the longer the run, the lower its far end, and the easier it is to drop below the ceiling.
Air conditioning and ventilation
Condensate drains also need a fall, and ducts take up a lot of ceiling space. Figure 4 shows the ceiling void of a building under construction: ducts, light fittings and the ceiling grid share a few hundred millimetres, exactly where disciplines clash most often.
Photo: USDAgov / Wikimedia Commons, Public domain
Cross-checking disciplines
This is the most valuable part of step 2. The basic method is to put the same floor from two disciplines side by side at the same scale (or overlay layers if you have CAD files), then go through a fixed checklist instead of looking at random.
Common clash points
| Check point | Compare which sheets | Sign of a discrepancy |
|---|---|---|
| Grid and dimensions between grid lines | Architectural plan and structural plan | Different dimension totals, columns off grid |
| Floor levels, dropped bathroom slabs | Architectural section, framing plan, bathroom detail | Architecture drops the bathroom floor but structure does not |
| Slab openings, service shafts | Architecture, structure, plumbing | A riser with no opening in the structural slab |
| Floor drains and toilets versus beams | Drainage plan and beam plan | A drain outlet lands right on a beam |
| Ceiling level versus beam soffits and pipes | Architectural section, beam detail, pipe plan | Drain pipe or duct lower than the ceiling |
| Doors and windows versus columns and beams | Plans and elevations, structure | A door overlapping a column, lintel clashing with a beam at a different level |
What to do when you find a clash
Do not choose the "more correct" discipline yourself: the decision belongs to the designers. Record both numbers, the location and sheet numbers in a query. If the clash affects work about to start, tell the client and note it in the site diary so only that item is put on hold.
Safety warning: When you take drawings on site to measure and compare, keep wearing a hard hat with the chin strap fastened and safety-toe boots. Do not walk while reading drawings on a floor with uncovered openings, unprotected slab edges or uncapped starter bars. Stop in a safe spot, then read. Do not measure under a suspended load, and do not touch temporary power cables while pulling a tape. If openings or guardrails do not match the safety plan, deal with them using the step 1 procedure before carrying on.
Writing design queries before work starts
A design query (often called an RFI, request for information) is a written request to the designers to clarify a gap or a clash. The written answer is the basis for construction and inspection.
What a query contains
- Query number, date, sender, work item.
- Sheet numbers and revisions for every discipline involved.
- Exact location by grid and floor (for example "beam on grid B, bay 3–4, level 2").
- The discrepancy in numbers: what discipline A says, what discipline B says, and the difference.
- A closed question that can be answered with one decision.
- A proposed fix so the designer can choose quickly, with a marked-up extract of the drawing.
- A reply deadline, counted back from the date that item will be built.
Good and bad questions
A bad question: "The MEP drawings are wrong, please review." The designer does not know where. A good question: "The Ø110 drain from the level 2 WC per the drainage sheet has its invert at the end of the run at +2.910, below the +2.950 needed for the ceiling framing per the architectural ceiling sheet. Please choose: lower the ceiling to +2.850, reroute the pipe, or allow the pipe through beam D2 with a reinforcement detail."
Tracking queries
Log every query in a table: number, date sent, deadline, date answered, outcome. When revised drawings come back, update the drawing register and collect the old sheets from site the same day.
Worked example: cross-checking a 4-storey townhouse
A 4-storey reinforced concrete townhouse on a 5 × 20 m plot. The owner hires you as an independent supervisor. You receive the construction set (architecture, structure, electrical, plumbing) and have 5 days before excavation.
Step 1: add up the grid chain in two disciplines
Along the length of the house, architecture gives grid 1–5 as 4,200 + 4,800 + 3,600 + 4,400 = 17,000 mm. Structure gives 4,200 + 4,800 + 3,700 + 4,400 = 17,100 mm. The totals differ by 17,100 − 17,000 = 100 mm, in bay 3–4 (3,700 versus 3,600). That is a column setting-out discrepancy and must be queried before grid pegs go in.
Step 2: check ceiling level against the level 2 drain
Working in millimetres above ground floor level (so +3.600 m is 3,600 mm): the level 2 finished floor is at 3,600 with a 50 mm finish, so the structural slab is at 3,600 − 50 = 3,550. Beam D2 is 400 mm deep including the slab, so its soffit is at 3,550 − 400 = 3,150. The ground floor plasterboard ceiling is at 2,900; assume the ceiling detail needs at least 50 mm above the board for framing, so everything must stay above 2,950.
Drainage sheet: a Ø110 pipe from the level 2 WC runs under the beam, 5 m long at a 2 percent fall, so it drops 5,000 × 2% = 100 mm. Hangers take 30 mm below the beam soffit. Pipe invert at the start: 3,150 − 30 − 110 = 3,010. Invert at the end: 3,010 − 100 = 2,910. Against the required 2,950: short by 2,950 − 2,910 = 40 mm. The pipe will hit the ceiling framing.
Step 3: check the bathroom drain outlet
The level 3 drainage plan places the bathroom floor drain 150 mm from grid C. The level 3 beam plan has beam D5, 220 mm wide, running along grid C, so it occupies 110 mm on each side of the grid (if centred). The Ø90 pipe has a 45 mm radius, so its nearest edge is 150 − 45 = 105 mm from the grid, which overlaps the beam by 110 − 105 = 5 mm. The drain or the beam position must be queried.
Step 4: summary table and queries
| Query | Location | Discrepancy in numbers | Options for the designer | Reply by |
|---|---|---|---|---|
| Q-01 | Bay 3–4, whole building | Architecture 3,600, structure 3,700; totals 17,000 versus 17,100 (100 mm) | Confirm the correct dimension, reissue the wrong sheet | Before column setting-out |
| Q-02 | Ground floor ceiling, under beam D2 | Pipe invert at end 2,910 mm, needs 2,950 mm (40 mm short) | Lower ceiling, reroute pipe, or pipe through beam with reinforcement detail | Before level 2 slab rebar inspection |
| Q-03 | Level 3 WC, grid C | Pipe edge 105 mm from grid, inside the 110 mm half-width of the beam (5 mm overlap) | Move the drain, or confirm a sleeve or cast-in detail | Before level 3 slab rebar inspection |
Check the numbers: 17,100 − 17,000 = 100; 3,150 − 30 − 110 − 100 = 2,910 and 2,950 − 2,910 = 40; 150 − 45 = 105 and 110 − 105 = 5. Suppose the designers reply: the correct dimension is 3,700 (architecture reissues the plan), the ground floor ceiling drops to +2.850, and the level 3 drain moves to 250 mm from grid C. You update the drawing register, collect the old sheets and record it in the site diary.
Common mistakes when reading design documents
Reading architecture only
Sign: you know every room but not how deep any beam is. Fix: for each floor, read all three disciplines against the cross-check list before work on that floor starts.
Using old sheets or permit drawings
Sign: the crew holds a photocopy with no date or revision. Fix: keep only the latest construction drawings on site and stamp old ones "superseded".
Asking and answering verbally
Sign: "the architect said on the phone it's fine". Consequence: when something goes wrong, nobody is responsible. Fix: every question and answer goes on a query form or in writing, with revised drawings where needed.
Frequently asked questions
Where do I start when reading structural drawings?
With the general notes (concrete strength, steel type, cover, laps), then the foundation plan and the framing plan for each floor, and finally the rebar details and bar schedules.
What are MEP drawings?
MEP stands for Mechanical (air conditioning, ventilation), Electrical and Plumbing. MEP drawings show the routes of cables, pipes and equipment.
Can I build from building permit drawings?
You should not. Permit drawings in Vietnam only show size, layout and elevations for the permit. Build from the construction drawings confirmed by the client, while staying within what the permit states; check the specific conditions against current local rules.
What should a design query (RFI) include?
Query number, sheet numbers for every discipline involved, location by grid and floor, the discrepancy in numbers, a closed question, a proposed fix and a reply deadline.
Practice and self-assessment
- Get a real townhouse drawing set (from a design firm, a supervisor you know or a relative's house) and build a drawing register: sheet number, title, revision, date.
- Work out the invert of the longest level 2 drain as in the example above and compare it with the ceiling level.
- Go through the 6 points in the cross-check table for one floor and write at least 2 queries with all 7 items.
Self-assessment criteria
- Pass: your register records every revision and you can say which sheet is the latest construction issue.
- Pass: your grid chain sums and pipe level calculations check out number by number.
- Pass: each query has sheet numbers, a grid location, the discrepancy in numbers and a question answerable with one decision.
- Not yet: picking the number that "must be right" when two disciplines disagree, or writing "drawings wrong, please review" without a location.
Once you can read a design set confidently, you will have the list of concrete strengths, steel types, brick specifications and finishes that the design requires. That is the basis for the next roadmap step: Checking incoming materials, where you check steel, cement, sand, aggregate and bricks against the specs, review mill certificates, take samples for lab tests when needed and reject non-compliant deliveries.
Keep learning site supervision: after reading design documents come checking materials, inspecting formwork, rebar and concrete, then supervising finishes, MEP coordination and as-built records. See the 8-step construction site supervisor roadmap.