Setting out floor tiles properly means doing the job on paper before doing it on the floor: read the tiling plan for sizes, levels and laying direction, measure the real room again, set a datum with a laser level, then work out where the grout lines go so the cut tiles on both sides are equal, at least half a tile, and fall in hidden places. Only with a setting-out sketch can you count exactly how many tiles to buy. Tilers who skip this step end up with a strip of tiny cuts right at the entrance, grout lines that jump between rooms, or a shortage of a few boxes halfway through and a top-up order from a different colour batch.
By the end of this lesson, you will be able to:
- Read a tiling plan: tell finished (clear) dimensions from gridline dimensions, and understand level marks, falls, laying direction and movement joints.
- Measure an existing room, check whether it is square using the two diagonals, and record a measurement sketch.
- Set up, level and self-check a laser level; transfer the 1 m datum around the room and measure a level grid on the rough floor.
- Calculate a symmetrical layout with a formula and pick one of three centring options so every cut is at least half a tile.
- Count tiles from the setting-out sketch, compare that with the "area plus 5–10%" method, and know when the area method falls short.
Learning to be a tiler? Measuring and setting out is step 2 of the roadmap, after materials and cutter safety, and before substrate prep and screeding. See the 8-step tiler roadmap to learn in the right order.
Why measure and set out before mixing adhesive?
A tiled floor is made or ruined before the first tile touches adhesive. Lay a few rows, then discover the last tile against the wall is only 3 cm wide, and the only fix is to lift and relay. In the lesson on ceramic vs porcelain tiles and cutter safety you learned to choose materials; this lesson teaches you to turn a room into a sketch with real numbers.
Setting out decides three things
- Looks: grout lines square to the door, equal cuts on both sides, no slivers where people look.
- Durability: very small cuts have little adhesive contact and tend to come loose or crack at the edge.
- Material cost: the number of cuts, unusable offcuts and boxes to buy all come from the setting-out sketch.
Reading a tiling plan
A tiling plan is a top-down drawing showing the tiled area, tile type, laying direction and the level of each zone. A townhouse plan may only say "60 x 60 tiles"; apartment projects often have a detailed tiling drawing with the tile grid already drawn.
Clear dimensions vs gridline dimensions
The dimension between two gridlines (wall centrelines) is not the length you tile. You tile within the clear dimension, the distance between the two plastered wall faces. For example, gridlines 7.0 m apart, 100 mm walls and 15 mm of plaster on each face leave about 7.0 − 0.05 − 0.015 − 0.05 − 0.015 = 6.87 m clear. Always re-measure after plastering; never set out from gridline figures.
Level marks, falls and laying direction
Common symbols (they vary slightly between designers; if you see one you do not recognise, ask the engineer rather than guess):
| Mark on the drawing | Meaning | What the tiler does |
|---|---|---|
| ±0.000 | Reference level, usually the finished floor of the ground floor or main room | Use it as the datum for every room on that floor |
| −0.020, −0.050 in bathrooms, balconies | Finished floor 20 mm or 50 mm below the reference level | Leave the step so water does not run into the room |
| Arrow with i = 1% or i = 2% | Direction and gradient of the fall to the drain | Note it so the screed step gets the fall right |
| Square grid drawn on the plan | Tile size and planned grout line positions | Compare with real measurements, report any mismatch |
| Dashed line marked "movement joint" | Where a joint is left for the floor to move | Make a grout line coincide with it, never tile across it |
Tiled area and material transitions
Mark where the tile type changes (bathroom thresholds, where tiles meet a timber floor); a transition should fall under the closed door. Ask the owner where the kitchen units, wardrobes and bed will go: those are the hidden places to push your cuts into.
Measuring the room and checking it is square
The drawing shows intent; the real measurements are what you tile. Plaster thickness varies and corners are rarely perfectly square.
Basic measuring tools
A 5–7.5 m tape or a laser distance meter, a chalk line, a carpenter's pencil, squared paper (1 square = 10 cm), and a line laser or a clear water level tube to transfer levels.
Measure each side at three points
Measure each side at three positions: near both corners and in the middle, about 10 cm above the floor. If the three readings differ by more than 10 mm, the walls are not parallel; write all three down and set out from the smallest.
Checking square with the two diagonals
Measure both diagonals from corner to opposite corner. In a square rectangular room they are equal. A few millimetres of difference is normal; from roughly 10–15 mm upward the room is out of square, and you must push the error towards a hidden wall rather than spreading it over two visible walls. The 3–4–5 rule in the lesson on laying floor tiles with adhesive is for snapping square lines; the two diagonals tell you whether the room itself is square.
Setting the datum with a laser level
Setting the datum means marking a reference level on the walls all around the room, usually a +1.000 line, exactly 1 m above the finished floor. Every level after that is measured down from this line.
Choosing a laser
Tilers mostly use line lasers with 2, 3, 5 or 12 lines; green beams are easier to see than red in a bright room. Rotary lasers with a receiver are for large floors or outdoors. A basic line laser costs about 1–6 million VND (roughly 40–240 USD) depending on the number of lines and the brand (2026 reference, varies by region in Vietnam). Check the accuracy on the label or in the manual.
Photo: Fanti Salms / Wikimedia Commons, CC BY-SA 3.0
Setting up and levelling
- Place the laser in the middle of the room on a tripod or solid base, never on loose tiles or a springy board (see Figure 1).
- Release the pendulum lock so it self-levels. If it is tilted beyond its range it flashes or beeps; adjust the legs until the bubble is centred.
- Switch on the horizontal line and adjust the height so it hits the +1.000 mark taken from the engineer's benchmark or from a room that already has its datum.
- Mark the beam on every wall every 1–1.5 m, then snap a chalk line through the marks.
Photo: MTA Capital Construction Mega Projects / Wikimedia Commons, CC BY 2.0
Self-checking the laser with two walls
A laser that has been dropped once can be off without you noticing. Check it before a big job and every time it falls:
- Place the laser midway between two opposite walls 5–6 m apart and mark the horizontal beam on wall A (point a1) and wall B (point b1).
- Move the laser close to wall A, about 0.5 m away, and mark a2 and b2.
- Compare the height difference between a1 and b1 with that between a2 and b2. They should be almost equal; if they differ by more than the stated accuracy, have the laser recalibrated before using it again.
Carrying the datum through several rooms and measuring a level grid
All rooms on one floor must take their datum from one common benchmark, even when you move the laser. Each time you move it, line the beam up with the existing mark at the connecting doorway before marking further. Figure 3 shows a laser reference line running continuously along a wall base.
Photo: MTA Capital Construction Mega Projects / Wikimedia Commons, CC BY 2.0
Once the datum line is in place, lay out a grid of about 1 x 1 m on the rough floor and, at each point, measure down from the datum line to the floor. Subtract 1,000 mm to get the total finish build-up at that point. This grid is the input for the screeding step.
Symmetrical setting out: the formula and three centring options
The goal: tile rows square to the door and the most visible wall, equal cuts on both sides, every cut at least half a tile, and cuts hidden under units, behind doors and under the skirting.
The cut-tile formula
Let L be the clear length, e the gap left at each wall (usually 5 mm for movement, hidden by the skirting), a the tile size, r the joint width and n the number of whole tiles. With n whole tiles and 2 cut tiles at the ends, a row has n + 1 joints:
Cut on each side = (L − 2e − n × a − (n + 1) × r) ÷ 2
Try a few values of n and pick the one that gives cuts of at least a ÷ 2, as close to a as possible. Remember to subtract the blade width (about 2–3 mm) when deciding whether an offcut can be reused.
Three centring options
- Option A, joint on the room centreline: an even number of whole tiles, with a grout line exactly in the middle.
- Option B, tile centred on the centreline: an odd number of whole tiles, with the middle tile centred.
- Option C, whole tiles from one wall: start with whole tiles at the most visible wall (usually the entrance or balcony door) and push all cutting to the hidden wall.
A and B give equal cuts on both sides, which suits the view from the door; C suits a side fully hidden by units. If a cut comes out smaller than half a tile, switch options.
Grout lines running through doors and corridors
When the living room, corridor and bedrooms share the same tile, set out the whole run as one floor, not room by room. Grout lines running straight down a corridor, as in Figure 4, look far cleaner.
Photo: Basile Morin / Wikimedia Commons, CC BY-SA 4.0
Drawing the setting-out sketch
Draw the room to scale on squared paper, rule the grout lines, shade the cut tiles and write their sizes, then send it to the owner for approval before tiling. On large floors like Figure 5, the crew also dry-lays the whole grid with spacers to check before mixing adhesive.
Photo: U.S. Navy photo by Mass Communication Specialist 2nd Class Erick S. Holmes / Wikimedia Commons, Public domain
Safety when measuring and setting levels
Safety warning: never look straight into a laser beam or shine it into anyone's eyes, even with a low-power tool; read the laser class and warnings on the label. Before drilling for a benchmark screw or nailing a string line into the floor, find out where water pipes and electrical conduits run in the floor and walls; drilling into a live cable can cause electric shock. If you cut sample tiles with a cutter, wear eye and dust protection and follow the cutter safety lesson. Keep tripods and chalk lines out of walkways when not in use.
Counting tiles and allowing for waste
Area plus a waste allowance is quick and fine for a rough quote; counting tiles from the sketch is accurate and essential for large tiles and small rooms.
Method 1: area plus waste
Area to buy = tiled area × (1 + waste rate). Divide by the area per box and round up. The waste rate depends on the pattern and the room shape:
| Situation | Typical waste | Notes |
|---|---|---|
| Straight lay, large square room, tiles up to 60 x 60 | 5% | Few cuts relative to the total |
| Straight lay, room with many corners, columns, recesses | 7–10% | Many notched cuts |
| Staggered rectangular or wood-look tiles | 8–10% | Some end offcuts can be reused |
| Diagonal (45°) or herringbone | 10–15% | Every tile at the wall is cut at an angle |
| Small room, 60 x 60 or larger, cuts on all four sides | Can exceed 10% | Count from the sketch |
These are rule-of-thumb figures tilers use for quick estimates, not official norms.
Method 2: counting from the setting-out sketch
From the sketch, count whole-tile positions, long-side cuts, short-side cuts and corner pieces. Check whether the offcut from one cut is big enough to make another; if not, every cut position uses a whole tile. Add a few spares for breakage and for the owner's future repairs, then convert to boxes.
Buy from one batch
Different production batches can differ in shade and size. Buy everything at once and check that the batch number on every box matches.
Worked example: open-plan living room and kitchen, 6.85 x 4.25 m, 60 x 60 cm tiles
A bare-shell apartment has an open living room and kitchen measuring 6.85 m clear (from the front door to the balcony door) by 4.25 m. The owner chose rectified 60 x 60 cm porcelain tiles, 2 mm joints, 4 tiles (1.44 m²) per box. The kitchen units run along the inner wall. A 5 mm gap is left at each wall.
Step 1: check the room and set the datum
- Theoretical diagonal: square root of (6.85² + 4.25²) = square root of 64.985 ≈ 8.061 m. Measured: 8.068 m and 8.054 m, a 14 mm difference. The room is slightly out of square, so the error is pushed towards the kitchen-unit wall.
- Datum +1.000 marked around the room; 6 grid points measured from the datum line to the rough floor: 1,068, 1,055, 1,072, 1,049, 1,061 and 1,058 mm. Finish build-up: 68, 55, 72, 49, 61 and 58 mm; the rough floor varies by 72 − 49 = 23 mm.
- Tile about 10 mm plus adhesive about 5 mm is 15 mm, so the screed in the next step will be 49 − 15 = 34 mm to 72 − 15 = 57 mm thick.
Step 2: set out the 6.85 m length (seen from the front door)
- Usable length: 6,850 − 2 × 5 = 6,840 mm.
- Option B, 11 whole tiles: 11 × 600 + 12 × 2 = 6,624 mm; 6,840 − 6,624 = 216 mm left, 108 mm each side. Less than half a tile (300 mm), rejected.
- Option A, 10 whole tiles: 10 × 600 + 11 × 2 = 6,022 mm; 6,840 − 6,022 = 818 mm left, 409 mm each side. Accepted: a joint on the room centreline.
- Check: 5 + 409 + 6,022 + 409 + 5 = 6,850 mm, matching the room length.
Step 3: set out the 4.25 m width
- Usable width: 4,250 − 2 × 5 = 4,240 mm.
- Option C, whole tiles from the window wall: 7 whole tiles plus 7 joints = 4,200 + 14 = 4,214 mm, leaving 26 mm at the kitchen wall. A 26 mm strip cannot be cut cleanly and bonds poorly, rejected.
- Option A, 6 whole tiles: 6 × 600 + 7 × 2 = 3,614 mm; 4,240 − 3,614 = 626 mm left, 313 mm each side. At least half a tile, accepted.
- Check: 5 + 313 + 3,614 + 313 + 5 = 4,250 mm, matching.
Step 4: count the tiles
The grid is 12 tiles along the length × 8 across = 96 positions. Cutting a 409 mm piece leaves 600 − 409 − 3 (blade) = 188 mm; cutting a 313 mm piece leaves 600 − 313 − 3 = 284 mm. Both offcuts are smaller than the cuts needed, so each cut position uses one tile.
| Position type | Calculation | Tiles |
|---|---|---|
| Whole tiles 600 x 600 | 10 × 6 | 60 |
| Cuts 600 x 313 along both long sides | 10 × 2 | 20 |
| Cuts 409 x 600 along both short sides | 6 × 2 | 12 |
| Corner pieces 409 x 313 | 4 corners | 4 |
| Spares for breakage and for the owner | about 4% | 4 |
| Total | 60 + 20 + 12 + 4 + 4 | 100 tiles = 25 boxes |
Step 5: compare with the area method and price it
- Area method: 6.85 × 4.25 = 29.1125 m²; plus 5% = 30.57 m²; divided by 1.44 = 21.2, rounded up to 22 boxes = 88 tiles. Short by 100 − 88 = 12 tiles, i.e. 3 boxes.
- Buying from the sketch: 25 boxes × 1.44 = 36 m². At an assumed 250,000 VND/m², 36 × 250,000 = 9,000,000 VND; the area method would cost 22 × 1.44 × 250,000 = 7,920,000 VND but leave you short.
- 60 x 60 porcelain prices vary widely, roughly 150,000–500,000 VND/m² or more depending on brand and finish (2026 reference, varies by region in Vietnam). Tell the owner about the 1,080,000 VND difference and why.
The lesson: 5–10% waste applies to large rooms with few cuts. With 60 x 60 tiles in a room of almost 30 m² cut on all four sides, the tiles actually bought exceed the floor area by about 24% (36 vs 29.11 m²), and only the setting-out sketch shows you that before you order.
Common measuring and setting-out mistakes
Setting out from gridline dimensions
Sign: the last cut is a few centimetres smaller than planned. Cause: using the centreline figure and forgetting wall and plaster thickness. Fix: always measure clear dimensions after plastering, three points per side.
A different datum in every room
Sign: a lip of a few millimetres at the doorway between two rooms. Cause: each room picked its own 1 m line. Fix: one common benchmark for the whole floor.
Ordering by area for a small room with large tiles
Sign: running out of tiles with a few rows left at the wall, and a top-up order that does not match in colour. Cause: area plus 5% without counting. Fix: count from the sketch and check whether offcuts can be reused.
Frequently asked questions
How do I set out floor tiles so the cuts are not too small?
Calculate the cut with the formula for the two options (joint on the centreline, tile centred on the centreline), choose the one that gives cuts of at least half a tile, and do it for both directions of the room.
How do I calculate the number of floor tiles for a room?
Quick estimate: area × (1 + waste), divided by the area per box, rounded up. Accurate: count whole tiles, cuts and corner pieces on the sketch, then add spares.
What percentage of floor tile waste is reasonable?
Usually 5–10% for a straight lay and 10–15% for diagonal or herringbone. Small rooms with large tiles can be much higher, so count tiles.
What is the 1 m datum and where is it measured from?
It is a level line on the wall exactly 1 m above the finished floor, taken from the engineer's benchmark or a finished room and shared by the whole floor. Every build-up thickness is measured down from it.
How do I set the datum without a laser level?
Use a clear water level tube filled with water and no air bubbles: the water surface at both ends is always at the same height. Slower, but accurate if you are careful.
Practice exercise and self-assessment
- Pick a real room, measure each side at three points and both diagonals, and draw the sketch on squared paper.
- Set a +1.000 datum with a laser or water level, measure at least 6 grid points and work out the build-up at each.
- Set out 60 x 60 tiles with 2 mm joints for that room using options A, B and C; record the cut sizes for each.
- Count the tiles and compare with the area-plus-5% method.
Self-assessment criteria
- Pass: the sketch has three readings per side, both diagonals, and check sums that add up exactly to the room length and width.
- Pass: every cut is at least half a tile, and cuts fall in hidden places or are equal on both sides of the view from the door.
- Pass: the tile-count table adds up correctly, includes spares and is rounded up to whole boxes.
- Not yet: setting out from gridlines, a separate datum per room, or working out only one direction of the room.
With a setting-out sketch and a level grid in hand, you move on to the next step of the roadmap: Substrate prep, screeding and falls, where you use this level grid to lay a flat screed and form falls to bathroom and balcony drains.
Keep learning tiling: after setting out come screeding, laying floors with adhesive, wall tiling in bathrooms, grouting and large-format tiles. See the 8-step tiler roadmap.