At Level 3 you start taking on jobs where single-phase power is no longer enough: 5–7 storey townhouses with a lift, small workshops with an air compressor, eateries with commercial cookers, houses with a pump station, homestays with lots of air conditioners. The utility usually supplies these buildings with three-phase four-wire power. Mistakes on three-phase systems have far heavier consequences than on single-phase: a broken neutral can burn out a whole row of appliances in one second, reversed phase sequence makes a pump run backwards, and unbalanced phases trip the main breaker even though the total load still has headroom. This lesson takes you from the concepts to measuring, sharing out the load, and checking a three-phase board before it is energised.
By the end of this lesson, you will be able to:
- Explain phase voltage, line voltage, the 120° phase shift and the √3 relationship.
- Calculate the power and current of balanced three-phase loads and of single-phase loads connected to a three-phase supply.
- Distribute single-phase circuits across the three phases so that the current imbalance stays within acceptable limits.
- Understand why a broken neutral in a three-phase system is extremely dangerous and how to prevent it.
- Measure voltage, phase sequence and the current on each phase with a multimeter, a clamp meter and a phase rotation tester.
- Recognise conductor colours according to TCVN 7447 (IEC 60445) and the older conventions still found on Vietnamese sites.
The three-phase four-wire system: three sources 120° apart
A generator at the power station has three windings placed 120° apart on the stator. As the rotor turns, each winding produces a 50 Hz sine-wave voltage, but the three voltages reach their peaks one after another, a third of a cycle apart. At the distribution substation, the transformer secondary is connected in star (wye); the star point is earthed and brought out as the neutral conductor N. That gives four conductors: L1, L2, L3 and N. In the TN-C-S earthing system common in cities, the PEN conductor is split into N and PE at the main board of the building.
There are two quantities you must keep clearly apart:
- Phase voltage Up: measured between one phase conductor and neutral, about 220–230 V. Single-phase household appliances use this voltage.
- Line voltage Ud: measured between any two phase conductors, about 380–400 V. Three-phase motors, commercial cookers and three-phase welders use this voltage.
The relationship between the two is Ud = √3 × Up ≈ 1.732 × Up. The reason: two phase voltages are 120° apart, and the vector difference between them is √3 times as long as each vector. Many Vietnamese documents still state 380/220 V; newer standards harmonised with IEC state 400/230 V. In practice, line voltage measured on site usually ranges from 370 to 410 V depending on the position on the network and on peak hours.
Conductor colours and identifying phases on site
TCVN 7447 (the Vietnamese equivalent of IEC 60364) and IEC 60445 specify conductor colours for new installations. However, older buildings in Vietnam use many different conventions, so never trust a wire colour without measuring.
| Conductor | Colour to IEC 60445 (recommended for new work) | Common older convention |
|---|---|---|
| L1 | Brown | Red |
| L2 | Black | Yellow |
| L3 | Grey | Green or blue |
| N | Light blue | Black or blue/green |
| PE | Green–yellow stripes | Green–yellow, or none at all |
The old convention has dangerous colour overlaps: a "green/blue" wire may be phase L3 or the neutral, depending on the previous crew. When you take over an old board, put an L1/L2/L3/N/PE label on every conductor right after measuring it, and write the convention used on the board diagram. If you replace cables, use IEC colours for the new part and clearly note where the changeover point is.
Photo: Asurnipal / Wikimedia Commons, CC BY-SA 4.0
Power and current in a three-phase system
For a balanced three-phase load (a motor, a three-phase cooker, heating elements connected across all three phases):
P = √3 × Ud × I × cosφ, which gives I = P / (√3 × Ud × cosφ).
Example 1: a 7.5 kW pump motor, Ud = 400 V, cosφ = 0.85, efficiency η = 0.88. Electrical input power Pin = 7.5 / 0.88 ≈ 8.5 kW. Current I = 8,500 / (1.732 × 400 × 0.85) ≈ 14.4 A. The motor nameplate typically states about 14–15 A at 400 V, so it matches. A handy rule of thumb on site: a 400 V three-phase motor draws about 2 A for every kW of shaft output.
Example 2: a 9 kW three-phase resistive load (cosφ = 1) → I = 9,000 / (1.732 × 400) ≈ 13 A per phase. The same 9 kW on single-phase 230 V gives I = 9,000 / 230 ≈ 39 A. This is why large loads should run on three-phase: the current in each conductor is about three times smaller, cables and breakers are smaller, and voltage drop is lower.
For single-phase loads on a three-phase supply (lighting, sockets, single-phase air conditioners), each load draws current on one phase conductor only and returns it on N: I = P / (Up × cosφ). The total building load is the sum of the three phases, but the main breaker trips on the current of the most heavily loaded phase, not on total power. That is why you have to balance the phases.
Photo: Asurnipal / Wikimedia Commons, CC BY-SA 4.0
Phase balancing: sharing single-phase loads across three phases
When a building has a three-phase supply but most of the load is single-phase, the electrician has to decide which circuit goes on which phase. The goal: the three phase currents should be close to each other both under normal load and at peak times. A simple measure:
Imbalance (%) = (Imax − Iavg) / Iavg × 100, where Iavg is the average of the three phase currents.
In practice for houses and shops, keeping the imbalance below about 10–15% is good; above 20% you need to redistribute. Many local utilities also require three-phase customers not to run excessively unbalanced, because it affects the shared distribution transformer.
Phase balancing procedure at the design stage
- Draw up a load schedule as in Level 2: each circuit has its installed power, utilisation factor and main operating period (daytime, evening, all day).
- Separate out the three-phase loads (motors, lifts, three-phase cookers): they balance themselves and do not need to be distributed.
- Sort the single-phase loads by power, largest first. Place each circuit in turn on the phase with the smallest running total (a simple but effective "greedy" algorithm).
- Check by time period: the evening is when air conditioners and water heaters run at the same time; do not put all the bedroom air conditioners on one phase.
- Do not split one room across three phases unless necessary: sockets in the same room should be on the same phase, to avoid 400 V between two nearby sockets (dangerous when extension leads are used, and confusing during repairs).
- Clearly mark the phase of every circuit on the single-line diagram and on the board labels.
Worked example
A 4-storey townhouse with a three-phase supply. The single-phase loads at the evening peak are: 4 air conditioners at 1.2 kW, 2 water heaters at 2.5 kW, a 3.5 kW double induction hob, whole-house lighting 1.2 kW, general-purpose sockets 2.4 kW split over 4 floors, fridge and washing machine 1.0 kW. Total about 17.4 kW.
| Phase | Circuits connected | Power (kW) | Estimated current (A) |
|---|---|---|---|
| L1 | Induction hob 3.5 + air conditioner R1 1.2 + lighting 1.2 | 5.9 | ≈ 27 |
| L2 | Water heater 2.5 + air conditioner R2 1.2 + sockets F1–F2 1.2 + fridge, washing machine 1.0 | 5.9 | ≈ 27 |
| L3 | Water heater 2.5 + air conditioners R3, R4 2.4 + sockets F3–F4 1.2 | 6.1 | ≈ 28 |
Imbalance ≈ (28 − 27.3) / 27.3 ≈ 2.5%. In reality the loads never run exactly as in the table, but this distribution avoids the situation where one phase carries twice as much as the other two.
Neutral current and the danger of a broken neutral
When the three phases are perfectly balanced with linear loads, the three currents, 120° apart, add up to zero: the neutral carries almost no current. When they are unbalanced, the neutral current equals the vector sum of the three phase currents. Two things an electrician must remember:
- Third-harmonic currents from electronic loads (LED lamps, computer power supplies, inverter air conditioners) do not cancel but add up in the neutral. In an office building with many computers, the neutral current can equal or exceed the phase current. So do not reduce the cross-section of the neutral compared with the phase conductors in houses and offices, unless the design has calculated for it.
- A broken neutral in a three-phase system: the star point on the load side "floats", and the voltage on each phase is no longer 230 V but is shared out according to the load impedances. A lightly loaded phase can rise to 300–380 V while a heavily loaded phase drops below 150 V. Appliances on the over-voltage phase burn out in batches within a few seconds: TVs, power supplies, fridges, LED lamps.
Warning: Never install a fuse or a single-pole MCB in the neutral of a three-phase system. Never join the N conductor by twisting and taping it in the main board. Neutral joints must be lugged, tightened to the correct torque and inspected regularly, just like phase conductors. If N needs to be switched, use a 4-pole device that breaks N and all phases at the same time.
To protect appliances when a neutral fault occurs on the network side (outside your control), install an over-voltage / under-voltage protection relay (often called a voltage protector, or a "lost-neutral relay") on each phase or as a three-phase unit, controlling the main contactor or the shunt trip of the breaker. This device is cheap compared with the value of the appliances in the house, so recommend it to the customer for every three-phase board.
Phase sequence and three-phase loads
The phase sequence (L1 → L2 → L3) determines the direction of the rotating magnetic field in a three-phase motor. Swapping any two phase conductors makes the motor run in reverse. With fans, centrifugal pumps, compressors and lifts, reverse rotation can damage the equipment or create a hazard. With three-phase sockets, the sequence must be the same at every socket in the building so that equipment turns the right way wherever it is plugged in.
How to check:
- Use a phase rotation tester: clip the 3 leads to L1, L2, L3; a lamp or display shows forward/reverse. Many clamp meters and installation multifunction testers have this function built in.
- If you have no tester: run the motor unloaded for a very short time and watch the direction of rotation against the arrow on the housing. Only do this when you are sure the load and the mechanism can tolerate reverse rotation for a moment.
- Record the checked phase sequence in the commissioning report.
Photo: Asurnipal / Wikimedia Commons, CC BY-SA 4.0
Testing a three-phase board before energising
- Check continuity and insulation with the supply off: measure insulation between phases, phase – N, phase – PE and N – PE at 500 V DC; results must be ≥ 1 MΩ (new cables usually reach hundreds of MΩ). Remember to disconnect or isolate sensitive electronic equipment first.
- Check lug tightness at the main breaker and busbars, especially the neutral joints.
- Switch on the supply from the utility side with the branch breakers still off. Measure voltage at the incoming terminals of the main breaker: L1–L2, L2–L3, L3–L1 (≈ 400 V, differing by no more than a few percent), L1–N, L2–N, L3–N (≈ 230 V), N–PE (close to 0 V).
- Check the phase sequence with a phase rotation tester.
- Close the main breaker, then each branch; for three-phase branches, re-check voltage and phase sequence at the outgoing terminals.
- Measure the current on each phase with a clamp meter when the load is at normal and peak levels, and calculate the imbalance. Clamp the N conductor as well to find the neutral current.
- Record the results in the report (template table in the Level 2 commissioning lesson), adding columns for phase sequence and phase imbalance.
Common mistakes
| Mistake | Consequence | Correct practice |
|---|---|---|
| Putting all air conditioners on one phase | Main breaker trips in the evening, voltage drops on that phase | Spread air conditioners evenly over 3 phases by time period |
| Trusting old wire colours without measuring | A phase connected as N, appliances receive 400 V | Measure L–L, L–N, N–PE before connecting, and label |
| Single-pole MCB in the N conductor | When the N MCB trips the neutral is lost, causing widespread over-voltage | Never switch N on its own; use 4-pole devices |
| Reducing the neutral cross-section | N conductor overheats due to harmonics | N the same size as the phases with electronic loads |
| Not checking phase sequence | Pumps and fans run backwards, seals fail, no water delivered | Check with a phase rotation tester and record it |
| Two adjacent sockets on different phases | 400 V between the two sockets, dangerous during repairs | Same room, same phase; mark it clearly on the diagram |
Pass criteria for this lesson
- Measure and correctly record the 7 voltage values (3 L–L, 3 L–N, N–PE) at a three-phase board, and state whether the voltages are within limits.
- Correctly calculate the current of a three-phase motor from its nameplate (kW, cosφ, η), within 10% of the current stated on the nameplate.
- Prepare a single-phase load distribution plan for the sample townhouse with a calculated imbalance of ≤ 10%.
- Check phase sequence with a phase rotation tester and correctly swap two conductors when needed.
- Explain the consequences of a broken neutral and propose suitable voltage protection devices.
Frequently asked questions
My house is on single-phase. When should I switch to three-phase?
When the total simultaneous demand exceeds what the local utility can supply on single-phase (usually around 40–63 A depending on the area), or when you have three-phase loads such as a lift, a large pump or an air compressor. Switching to three-phase requires an application to the utility and replacing the meter and the main board; the wiring inside the house can be kept if the circuits are already clearly divided.
Can a multimeter measure phase sequence?
No. A multimeter only measures the magnitude of the voltage. You need a dedicated phase rotation tester, or the phase sequence function on a clamp meter or installation multifunction tester.
Does phase imbalance increase the electricity bill?
The meter measures the total energy of all three phases, so imbalance does not directly add a significant number of kWh. But imbalance increases losses in the cables, causes voltage drop on the heavy phase, shortens appliance life and makes the main breaker trip unnecessarily.
Further reading
Review how to choose cables and breakers in the lesson Choosing cable sizes and circuit breakers, and how to organise a board in the lesson Installing a distribution board with MCBs, RCBOs and earthing.