At Level 2 and Level 3 you learned to read drawings, calculate loads, size cables, choose circuit breakers, build panels and install large loads. At Level 4 the question is no longer "how do I wire this?" but "what electrical system should this whole house have?". A master electrician takes on a four-storey townhouse that still exists only as architectural drawings, sits down with the owner for one session, and then delivers a complete design package: a single-line diagram, device layout plans for each floor, a load and cable-sizing calculation sheet and a bill of materials. That package is the basis for the quotation, it lets the installation crew work without coming back with questions, and it is what the job is inspected and handed over against.
This lesson walks through the full design process for a typical 5 × 18 m, four-storey townhouse, with every number worked out. You can use the same process for an apartment, a garden house or a small shop.
By the end of this lesson, you will be able to:
- Collect the owner's requirements with a structured survey form, without missing any large load.
- Divide circuits by floor, by function and by type of protection, and decide whether floor panels are needed.
- Build a load calculation table, apply diversity factors, choose a single-phase or three-phase supply, and size the riser cables and main breaker.
- Draw a single-line diagram with complete information: ratings, trip curves, RCD sensitivity, cable sizes and circuit labels.
- Draw floor plans showing sockets, switches, lights, conduit routes and junction box locations according to good practice.
- Check the design package yourself with a checklist before giving it to the client and the installation crew.
Design is a responsibility, not just a drawing
For individual houses, most owners do not hire a separate electrical design engineer. The architectural set may include one sketchy "electrical plan" page that only marks lights and sockets. In reality, the lead or master electrician is doing the design work. When you decide the riser cable size, the RCD type and the number of circuits, you are taking responsibility for the safety of that family for 20–30 years.
That is why this lesson always ties decisions to references you can show the client:
- TCVN 9206:2012 (Vietnamese national standard) – Installation of electrical equipment in dwellings and public buildings: device locations, heights and clearances.
- TCVN 9207:2012 – Installation of wiring in dwellings and public buildings: wiring methods, conduit, separation from other services.
- TCVN 7447 (IEC 60364) – Low-voltage electrical installations: protection against electric shock and overcurrent, cable selection, earthing.
- QCVN 12:2014/BXD (national technical regulation issued by the Ministry of Construction) – Electrical systems of dwellings and public buildings.
- The local power utility's connection rules: registered capacity, meter location and service cable into the house.
The master electrician's rule: every number on the drawing must be able to answer the question "why?". A 32 A breaker because the design current is 24 A and a 6 mm² cable carries 41 A when run in conduit in the wall. No number is there "out of habit".
Step 1: Survey and requirements form
The first meeting with the owner decides 80% of the quality of the design. Bring a printed survey form and go through every room on the architectural drawings. The questions you must ask:
| Group | Question | Why it matters |
|---|---|---|
| Supply | Does the utility supply single-phase or three-phase? Where is the meter? What capacity has been registered? | Determines the riser cable, main breaker and phase balancing |
| Large loads | How many air conditioners, and what is the power of each? How many zones on the induction hob? Individual water heaters or a central hot water system? Washer-dryer? Electric vehicle charging? | Large loads make up 70–80% of the power, and each needs its own circuit |
| Pumps | A transfer pump to the roof tank, a booster pump, a fish pond pump, a basement drainage pump? | Motor circuits, dry-run protection, float switches |
| Backup supply | Any plans for solar, a generator or a UPS? Now or in a few years? | Reserve panel space, spare conduits, a priority panel |
| Lighting | Recessed downlights, cove lighting, stair lights with sensors, roof terrace lights? Where is two-way switching needed? | Number of lighting circuits, wiring for two-way switches |
| Low-voltage systems | How many network points, cameras, video doorbells, smart home devices? | Separate conduits, a network cabinet, power for the cabinet |
| Use | Is the ground floor used for business? Are rooms rented out, needing sub-meters? | Separate circuits, separate metering |
Also write down the "soft" wishes on the form: sockets on both sides of the bed, enough sockets on the kitchen counter to run an air fryer and a blender at the same time, a socket on the balcony for the washing machine. These are the points clients most often complain about after moving in.
Photo: Community Archives of Belleville & Hastings County / Wikimedia Commons, Public domain
Step 2: Dividing circuits
Circuit division is the step that shows the designer's skill most clearly. The principles:
- Separate lighting from sockets: a socket fault (leakage, short circuit) must not black out a whole floor. The occupants still have light to deal with the problem.
- One dedicated circuit for each large load: each air conditioner, induction hob, water heater, washer-dryer, EV charger and pump gets its own circuit with its own breaker.
- General socket circuits have no more than 8–10 outlets each, and no circuit serves more than one floor (unless the floor is very small).
- Wet areas get a 30 mA RCD: sockets in bathrooms, kitchens, balconies and roof terraces, the water heater circuit, the pump circuit and outdoor sockets.
- Spare capacity: every panel leaves at least 20% of its modules free for future circuits.
One main panel or floor panels?
| Option | Advantages | Disadvantages | When to use |
|---|---|---|---|
| One main panel on the ground floor, every circuit runs straight back to it | Fewer panels, easy to manage in one place | Lots of cables running the height of the house, voltage drop on distant circuits, an overcrowded riser conduit | Two-storey houses, apartments |
| Main panel on the ground floor + a panel on each floor | Short cables, repairs on one floor do not affect the others, easy to extend | Extra cost for panels and riser cables, breaker discrimination must be considered | Townhouses of three storeys or more, houses rented out floor by floor |
For the four-storey house in our example, we choose a main panel on the ground floor (next to the stairs, close to the meter) and one floor panel on each of floors 2, 3 and 4. The ground-floor panel also serves as the floor panel for floor 1.
Step 3: Load calculation table
Example house: floor 1 has the living room, kitchen and WC; floor 2 has two bedrooms and a WC; floor 3 has two bedrooms and a WC; floor 4 has the altar room, laundry area and roof terrace. A family of five, single-phase supply, with plans to install an electric scooter charger and solar panels in a few years.
| Floor | Loads | Installed power (kW) | Suggested diversity factor | Design power (kW) |
|---|---|---|---|---|
| 1 | Lighting 0.4; sockets 2.0; double induction hob 3.5; range hood 0.2; 18000 BTU air conditioner 1.8; water heater 2.5 | 10.4 | 0.6 | 6.2 |
| 2 | Lighting 0.3; sockets 1.5; two 9000 BTU air conditioners 1.7; water heater 2.5 | 6.0 | 0.6 | 3.6 |
| 3 | Same as floor 2 | 6.0 | 0.6 | 3.6 |
| 4 | Lighting 0.3; sockets 1.0; washer-dryer 2.2; pump 0.75; electric scooter charger 0.8 | 5.1 | 0.6 | 3.0 |
| Total of floor design loads | 27.5 | 16.4 | ||
| Diversity factor between floors | 0.75 | ≈ 12.3 kW | ||
Design current at the main supply: I = P / (U × cosφ) = 12 300 / (230 × 0.9) ≈ 59 A. On a single-phase supply, a 63 A main breaker is right at the design current, with nothing left over for solar or extra air conditioners. This is where the master electrician must advise: apply to the utility for a three-phase supply, or keep single-phase but accept the limits (do not run water heaters on three floors at once, switch to solar water heaters or heat pumps).
In this example the owner chooses three-phase. Planned phase allocation:
- L1: floor 1 (induction hob, air conditioner, floor 1 water heater) ≈ 6.2 kW design load.
- L2: floor 2 + pump ≈ 4.0 kW.
- L3: floor 3 + the rest of floor 4 ≈ 5.6 kW.
The highest current on one phase ≈ 6 200 / (230 × 0.9) ≈ 30 A. We choose a 40 A three-phase four-pole main MCCB/MCB, and the cable from the meter to the main panel is CXV 4 × 10 mm² (XLPE/PVC copper cable, with margin for load growth and solar later on). After installation you will measure the current on each phase and rebalance, as you learned at Level 3.
Sizing the riser cables to the floor panels
| Route | Design current | Breaker | Cable | Length | Voltage drop |
|---|---|---|---|---|---|
| Main panel → F2 panel (single-phase L2) | ≈ 19 A | MCB 2P 32 A C | CV 2 × 6 mm² + PE 6 mm² | 6 m | ≈ 0.4% |
| Main panel → F3 panel (single-phase L3) | ≈ 19 A | MCB 2P 32 A C | CV 2 × 6 mm² + PE 6 mm² | 10 m | ≈ 0.6% |
| Main panel → F4 panel (single-phase L3) | ≈ 15 A | MCB 2P 25 A C | CV 2 × 6 mm² + PE 6 mm² | 14 m | ≈ 0.7% |
Voltage drop is calculated with the formula from Level 2: ΔU% = 2 × L × I × ρ / (S × U) × 100. The total voltage drop from the meter to the farthest socket must stay below 4–5%. The 6 mm² riser cable is chosen not for current but so that the cumulative voltage drop, added to the 2.5 mm² branch circuit, still stays within the limit.
Step 4: Single-line diagram
The single-line diagram is the "backbone" of the design package. Every line on the diagram must show: the circuit label, the type and rating of the protective device, the trip curve, the number of poles, the RCD sensitivity and type, the cable size and type, and the load it supplies.
Consistent circuit labels
Set a convention once and use it for the drawings, panel labels and wire markers: T2-L1 (floor 2, lighting circuit 1), T2-O1 (socket circuit 1), T2-AC1 (air conditioner 1), T2-WH (water heater). The label appears in four places: the single-line diagram, the floor plan, the label inside the panel and the numbered ferrules at both ends of the wire. When maintenance is needed five years later, anyone who opens the panel knows which breaker feeds what.
Sample floor panel (floor 2)
| Circuit | Load | Protection | Cable |
|---|---|---|---|
| Incoming | From the main panel | 2P 40 A isolator switch | CV 6 mm² |
| T2-L1 | Lighting for 2 bedrooms and the corridor | MCB 1P+N 10 A B | 1.5 mm² |
| T2-O1 | Sockets in bedroom 1 + corridor | RCBO 16 A C 30 mA Type A | 2.5 mm² |
| T2-O2 | Sockets in bedroom 2 | RCBO 16 A C 30 mA Type A | 2.5 mm² |
| T2-WC | WC sockets, exhaust fan | RCBO 16 A C 30 mA Type A | 2.5 mm² |
| T2-WH | 2.5 kW water heater | RCBO 20 A C 30 mA | 2.5 mm² (short run) / 4 mm² |
| T2-AC1, AC2 | 9000 BTU air conditioners | MCB 16 A C | 2.5 mm² |
| Spare | 2 empty modules |
A note on discrimination: the main panel feeds each floor panel through a 32 A C-curve MCB, followed by 10–20 A MCBs/RCBOs. For overloads, discrimination works well; for a large short circuit close to the panel, two MCBs of the same type may both trip – acceptable in a house, or use an MCCB or fuses upstream if the client requires full discrimination. Do not put a 30 mA RCD in both the main panel and the floor panel for the same circuit: they will trip together and the whole house goes dark. If a main RCD is needed for fire protection, use a 300 mA time-delayed (Type S) unit.
Step 5: Device layout plans
The electrical plan is drawn over the architectural plan, one sheet per floor, with these layers: devices (lights, switches, sockets, supply points for large loads), main conduit routes, junction boxes, panels and height notes.
Reference mounting heights
| Device | Height to device center above finished floor | Notes |
|---|---|---|
| Switches | 1.2–1.4 m | 10–15 cm from the door frame, on the door handle side |
| Sockets in living spaces | 0.3–0.4 m | Use shuttered sockets in homes with small children |
| Kitchen counter sockets | 1.05–1.15 m | 15–20 cm above the stone worktop, ≥ 0.6 m from the sink |
| Washing machine socket | 1.2–1.5 m | RCD protected, with a splash cover |
| Air conditioner socket | 2.0–2.2 m | Or connect directly through a breaker next to the unit |
| Distribution panel | Bottom edge 1.5 m, top edge ≤ 2.0 m | Dry and easy to reach, not in a WC, not above the cooker |
Bathrooms must follow the zoning rules: no sockets or switches in zones 0, 1 and 2 (inside the bath, the shower area and 0.6 m around them). The hair dryer socket goes outside zone 2 and is protected by a 30 mA RCD.
Conduit routes and junction boxes
- Conduit runs straight, parallel or perpendicular to the edges of walls and ceilings; avoid diagonal runs in walls, because whoever drills later cannot guess where they are.
- Horizontal runs in walls sit 0.3 m below the ceiling or 0.3 m above the floor; vertical runs go straight up or down from the device.
- Fit a junction box at every major change of direction or every 10–15 m of straight conduit; junction boxes must remain accessible after finishing (not plastered over, not above a gypsum ceiling without an access hatch).
- Electrical conduit stays ≥ 0.1 m from hot water pipes when running in parallel, and low-voltage conduit stays ≥ 0.1 m from power conduit or runs in a completely separate conduit.
- Wires must not fill more than 40% of the conduit's internal cross-section (for example, a D20 conduit takes at most about 4–5 wires of 2.5 mm²).
Photo: John Arnold Thomson / Wikimedia Commons, Public domain
Step 6: The complete design process and self-check
Self-check list before handing over the design package
- Every large load on the survey form has its own circuit and appears in the load calculation table.
- Design current of each circuit ≤ breaker rating ≤ current-carrying capacity of the cable for its installation method.
- Total voltage drop to the farthest point < 4–5%.
- Every socket, wet-area and outdoor circuit has a 30 mA RCD; the RCD type suits the load (Type A for induction hobs, inverter washing machines and EV chargers).
- There is an SPD in the main panel, a PE conductor to every socket and equipment enclosure, an earth electrode and a target earth resistance value.
- Each panel has ≥ 20% spare space; there are spare conduits for solar, EV charging and a generator if the client plans them.
- Circuit labels are consistent between the single-line diagram, the floor plans and the panel schedule.
- Phases are balanced (difference in design current between phases ≤ 20–30%).
- Panels and junction boxes are accessible and not in wet zones.
Photo: Dmitry G / Wikimedia Commons, CC BY-SA 3.0
The design package to hand over
| Document | Content | Who uses it |
|---|---|---|
| Short design statement (1–2 pages) | Supply, capacity, panel arrangement, standards referenced, calculation assumptions | Owner, supervising engineer |
| Load calculation and equipment selection sheet | As in the Step 3 table and the panel schedule | You, the crew, the maintenance person |
| Single-line diagram | Main panel and floor panels | Panel builders, inspection |
| Plan for each floor | Devices, conduit, junction boxes, heights | Conduit crew, device installers |
| Preliminary bill of materials | Types, specifications, estimated quantities | Take-off and quotation (next lesson) |
The drawings can be made in CAD software, or you can print the architectural plans and draw neatly by hand, then scan them. What matters is having a paper copy signed by the owner before work starts: it protects you if the client changes their mind halfway through.
Common mistakes
| Mistake | Consequence | The right way |
|---|---|---|
| Calculating load by adding up every rated power and choosing the breaker from that | An oversized, expensive main breaker and cable – or the opposite when a large load is missed | Build a load table by floor and apply justified diversity factors |
| Putting lights and sockets on one circuit | A socket leak blacks out the whole floor | Give lighting its own circuits |
| Not calculating riser cable voltage drop | Air conditioners on upper floors struggle to start, lights flicker | Calculate the cumulative ΔU from the meter to the farthest point |
| A 30 mA RCD in both the main panel and the floor panel | A leak on one circuit cuts power to the whole house | A main RCD (if any) should be 300 mA Type S |
| No spare capacity | Adding a load means replacing the panel | ≥ 20% free modules, spare conduits |
| Circuit labels on the drawing differ from the panel labels | Maintenance on the wrong circuit, dangerous | One labeling system for every document |
| Not asking about solar or EV charging plans | Walls must be chased again to run new cables | Ask on the survey form, leave spare conduits |
Pass criteria for this lesson
- Complete the survey form for a sample house covering all 7 question groups, with no large load missed when the instructor cross-checks.
- Build a load table by floor, arrive at the main design current and decide between single-phase and three-phase, with reasoning.
- Draw the single-line diagram of the main panel and one floor panel with complete information: ratings, trip curves, number of poles, RCD type and sensitivity, cable sizes and circuit labels.
- Calculate the voltage drop of the riser cable and the farthest circuit, with a total < 5%.
- Draw a floor plan for one floor showing devices, conduit routes, junction boxes and height notes matching the reference table.
- Run the 9-item self-check list and fix every item that fails.
Frequently asked questions
Can an electrician sign design drawings?
For individual houses where the electrical design does not require official appraisal, an electrician can prepare the installation documents for the owner. For projects that need a building permit or appraisal, or for public buildings, the design drawings must be prepared and signed by an organization or individual holding the appropriate design practice certificate. A master electrician should know this limit and work with an engineer when needed.
Do I need specialist software?
No. A spreadsheet is enough for the load calculation; the drawings can be done in common CAD software or drawn by hand over the architectural plans. What matters is that they are correct, complete and consistent.
What is the right diversity factor?
There is no absolute figure. The table above gives practical values for family homes. Houses with a business, houses rented out room by room, or families that run air conditioning constantly need higher factors. Write your assumptions in the design statement so you can compare them later when you measure the actual current.
Further reading
Review how to size cables and breakers in the lesson Choosing cable sizes and circuit breakers and how to build a panel in the lesson Building a panel with MCBs, RCBOs and earthing.