Plenty of electricians are highly skilled with their hands and still lose money on projects. The cause is rarely bad workmanship – it is an incomplete take-off: a few forgotten rolls of wire, flush boxes undercounted, no allowance for chasing walls, no allowance for waste, no allowance for the days spent running out to buy small parts. A little here and a little there, and together they add up to the entire profit. At the other extreme, padding the take-off "to be safe" by doubling everything makes the quotation too high, and you lose the client.
This lesson teaches you to take off quantities from the design package you produced in the previous lesson using a systematic method that can be cross-checked, and to calculate labor from norms instead of "guessing". The result is a cost estimate you can confidently sign a fixed-price contract on.
By the end of this lesson, you will be able to:
- Count devices from the floor plans and measure wire and conduit lengths circuit by circuit, with sensible allowances.
- Build a standard bill of quantities: item, specification, unit, quantity and data source.
- Apply waste rates by type of material instead of adding one flat figure.
- Calculate labor from hour norms for each task and convert it into worker-days, crew size and number of days.
- Set up the structure of a cost estimate: materials, labor, overheads, risk and profit.
- Cross-check the estimate with unit-rate indicators per square meter of floor area and per connection point.
Take-off principles
- Take off from the drawings, not from memory. Every number in the table must point to its source: which drawing sheet it was counted on, which route was measured.
- Take off by circuit, total by material. Measure the wire for each circuit – T2-O1, T2-O2 and so on – and only then add them up into "2.5 mm² wire". That way nothing is missed and it is easy to re-check.
- Keep design quantities and waste separate. Record "measured quantity" and "waste factor" in separate columns; never mix them.
- Mark items as you count them. Print the drawings and, as you count each type of device, strike it through with a colored pen for that device. Nothing is counted twice and nothing is missed.
- Write down your assumptions. "Gypsum ceiling throughout floors 2–4", "square-plate sockets, 2-pin/3-hole", "wire from brand X". If the client changes an assumption, the estimate changes.
Photo: U.S. Navy photo by Mass Communication Specialist 3rd Class Aramis X. Ramirez / Wikimedia Commons, Public domain
Step 1: Counting devices
From each floor plan, count into a table. Example for the four-storey townhouse from the previous lesson:
| Device | F1 | F2 | F3 | F4 | Total | Notes |
|---|---|---|---|---|---|---|
| Recessed LED downlights | 14 | 12 | 12 | 6 | 44 | Ceiling cut-outs, separate drivers |
| Ceiling-mounted and wall lights | 3 | 4 | 4 | 5 | 16 | Includes stair and balcony lights |
| One-way switches (modules) | 8 | 6 | 6 | 5 | 25 | |
| Two-way switches (modules) | 2 | 2 | 2 | 2 | 8 | One pair on the stairs at each floor |
| Double 3-pin sockets | 10 | 8 | 8 | 5 | 31 | |
| Sockets with waterproof covers | 1 | 1 | 1 | 3 | 6 | WC, balcony, roof terrace |
| Air conditioner supply points | 1 | 2 | 2 | 0 | 5 | Breaker next to the unit |
| Water heater points | 1 | 1 | 1 | 0 | 3 | |
| Switch/socket faceplates | counted by number of mounting positions | 48 | 1-, 2- and 3-gang plates listed separately | |||
| Flush wall boxes | = number of faceplates + spare boxes | 52 | ||||
| Junction boxes (distribution boxes) | 6 | 5 | 5 | 4 | 20 | From the conduit plan |
Two common counting mistakes: forgetting flush boxes for future positions (for cameras, doorbells, smart home devices), and not distinguishing between 1-, 2- and 3-gang plates – they have different prices.
Step 2: Measuring wire and conduit lengths by circuit
The wire length of a circuit is made up of four parts:
- Riser section: from the panel up to the ceiling (or down to the floor) – the distance from the bottom of the panel to the ceiling plus the length run in trunking.
- Horizontal section: measured on the plan along the actual conduit route (running square to the wall lines, never measured diagonally).
- Drops to devices: from the ceiling down to a switch (3.3 m ceiling, switch at 1.3 m → 2.0 m), down to a socket (≈ 3.0 m).
- Termination allowance: leave 0.5–0.8 m extra at each panel end, 0.2–0.3 m at each device box and 0.3 m at each junction box.
Example: circuit T2-O1
| Section | Conduit length (m) |
|---|---|
| F2 panel up to the ceiling | 1.5 |
| Horizontal in the ceiling to bedroom 1 | 7.0 |
| Horizontal between the sockets in the room (4 sockets) | 9.0 |
| Drops to 4 sockets × 3.0 m | 12.0 |
| Branch out to the corridor (1 socket) | 3.0 + 3.0 |
| Total conduit | 35.5 |
Wire: 3 conductors (L, N, PE) × 35.5 m = 106.5 m. Allowances: panel 0.6 m × 3 + 5 boxes × 0.25 m × 3 + 2 junction boxes × 0.3 m × 3 ≈ 7.4 m. Total ≈ 114 m of 2.5 mm² wire for circuit T2-O1. L and N use different colors and PE is green-yellow: list each color separately, because wire is bought by the roll in each color.
Repeat for every circuit, then total by type. The summary table for the example house (before waste):
| Material | Measured | Waste | To order | Purchase unit |
|---|---|---|---|---|
| 1.5 mm² wire (red + blue) | 720 m | 8% | 778 m → 8 rolls of 100 m | 100 m roll |
| 2.5 mm² wire (red + blue) | 860 m | 8% | 929 m → 10 rolls | 100 m roll |
| 2.5 mm² green-yellow wire (PE) | 560 m | 8% | 605 m → 6 rolls | 100 m roll |
| 4 mm² wire (hob, distant water heaters) | 95 m | 8% | 103 m → 1 roll + loose meters | roll/meter |
| CV 6 mm² riser cable (3 colors) | 105 m | 5% | 110 m | meter |
| CXV 4 × 10 mm² service cable | 18 m | 5% | 19 m | meter |
| D20 conduit | 610 m | 10% | 671 m → 230 lengths of 2.92 m | length |
| D25 conduit | 90 m | 10% | 99 m → 34 lengths | length |
| D20 flexible corrugated conduit (drops to ceiling lights) | 180 m | 10% | 4 coils of 50 m | coil |
Photo: Marc Ryckaert / Wikimedia Commons, CC BY-SA 4.0
Step 3: Waste by type of material
| Material type | Practical waste rate | Reason |
|---|---|---|
| Single-core wire in conduit | 5–10% | Roll ends, cutting long, actual routes longer than measured |
| Riser and large cables | 3–5% | Measured carefully, cut to length |
| Rigid conduit | 8–12% | Short offcuts, breakage, joints |
| Conduit fittings (elbows, couplers, saddles) | 10–15% | Dropped, broken, counted by estimate |
| Devices (switches, sockets, breakers) | 0–2% | Counted exactly; 1–2 spares for defects |
| Consumables (tape, lugs, cable ties, wall plugs) | Priced as a package per point | Too small to count individually |
Consumables are often forgotten. The practical method: price them by number of connection points (each light, socket, switch or load supply point is one point). For example, one point needs about 2–3 lugs or connectors, 3–4 cable ties, 2 wall plugs, some tape and conduit glue. Build a "consumables package per point" from your own crew's experience, then multiply it by the total number of points.
Step 4: Labor norms
A norm is the average number of labor hours needed to complete one unit of work with normal skill under normal conditions. The government's construction cost estimating norms include a section on electrical installation and are a good reference. But a master electrician should have in-house norms for their own crew, drawn from records of past projects. The table below gives practical starting values – adjust them with your own data.
| Task | Unit | Labor hours/unit | Notes |
|---|---|---|---|
| Cutting and chasing brick walls for D20 conduit | m | 0.15–0.25 | Wall chaser with dust extraction; concrete walls × 2 |
| Running rigid conduit in the ceiling, fixing with saddles | m | 0.08–0.12 | |
| Running concealed conduit in walls, fixing and filling | m | 0.10–0.15 | Chasing not included |
| Installing flush wall boxes | each | 0.3–0.5 | Includes drilling, chiseling and leveling |
| Pulling wire through conduit | m of wire | 0.01–0.02 | Difficult routes × 1.5 |
| Fitting and connecting switches and sockets | each | 0.25–0.35 | |
| Cutting ceilings and fitting downlights | each | 0.3–0.4 | |
| Installing and wiring an 8–12 module floor panel | panel | 4–6 | Includes labeling and wire numbering |
| Installing and wiring a three-phase main panel | panel | 8–10 | |
| Driving earth rods, measuring earth resistance | system | 4–6 | 3 rods, exothermic welding |
| Testing, inspection, writing up the report | 4-storey house | 6–8 |
Example: converting to worker-days
| Task | Quantity | Norm (hours) | Labor hours |
|---|---|---|---|
| Chasing walls | 320 m | 0.2 | 64 |
| Ceiling + concealed wall conduit | 700 m | 0.11 | 77 |
| Flush wall boxes | 52 pcs | 0.4 | 21 |
| Pulling wire | 2 400 m | 0.015 | 36 |
| Fitting devices (switch modules, sockets) | 70 pcs | 0.3 | 21 |
| Fitting lights | 60 pcs | 0.35 | 21 |
| Main panel + 3 floor panels | 4 panels | 9 + 3 × 5 | 24 |
| Earthing | 1 system | 5 | 5 |
| Testing and inspection | 1 house | 7 | 7 |
| Total direct labor hours | 276 | ||
| Site condition factor (travel, waiting, coordination, cleaning up) × 1.2 | ≈ 331 | ||
331 hours ÷ 8 hours/day ≈ 41 worker-days. With a crew of 1 lead electrician + 2 helpers (counting each helper at 0.7 productivity), the crew output is ≈ 2.4 worker-days per day → about 17 working days, not counting time spent waiting for other trades (masonry, plastering, gypsum ceilings). You will use this figure directly in the scheduling lesson.
Step 5: Structure of the cost estimate
- Main materials: bill of quantities × supplier unit prices (use dated quotations with a validity period).
- Consumables: consumables package × number of points.
- Labor: worker-days × the day rate for each skill level (lead electrician, helper) + insurance and lunch if you pay for them.
- Overheads: 5–10% of direct cost – fuel, depreciation of the wall chaser, drills and meters, cutting discs, drill bits, parking fees, time spent buying materials.
- Risk contingency: 3–5% for new houses, 8–15% for renovations (old walls, surprises when chasing).
- Profit: the margin you set for your business, calculated on the total cost.
Step 6: Cross-checking
Before putting the estimate into a quotation, check it with three indicators:
- Meters of wire per point: total meters of wire ÷ number of points. Townhouses are usually 15–25 m/point. Much lower means a circuit may be missing; much higher means something was measured twice.
- Labor hours per point: total labor hours ÷ number of points, usually 2–3 hours/point for a complete new-build job. Compare with your own crew's past projects.
- Price per m² of floor area: total estimate ÷ floor area. Every crew should have its own price range for each material grade; an estimate far outside the range needs reviewing.
The example house has about 130 points and 2 400 m of wire → 18.5 m/point (reasonable); 331 hours ÷ 130 ≈ 2.5 hours/point (reasonable).
Photo: Jlgay38 / Wikimedia Commons, CC BY 4.0
Common mistakes
| Mistake | Consequence | The right way |
|---|---|---|
| Measuring wire diagonally across the plan | 20–30% short on wire | Measure along the actual square conduit route and add the vertical sections |
| Forgetting the PE wire or counting PE as phase wire | Material shortage, wrong colors | Take off each wire color separately |
| One flat 10% waste factor for everything | Too many devices, too few conduit fittings | Waste by type of material |
| Not pricing the labor for chasing and filling | The biggest labor loss | A separate line for chasing and filling |
| Not allowing for waiting and travel time | Schedule slips, labor losses | A site condition factor of 1.15–1.3 |
| Using old material prices | Losses when copper prices rise | Dated supplier quotations; a price escalation clause in the contract |
Pass criteria for this lesson
- From a sample drawing set, count devices with no more than 2% difference from the answer key.
- Measure wire and conduit lengths for 3 sample circuits with a deviation of ≤ 10% from the answer key.
- Build a bill of quantities with "measured", "waste" and "to order" columns, correctly converted into purchase units.
- Calculate labor hours from norms and convert them into working days for a given crew structure.
- Build an estimate with all 6 components and cross-check it with the 3 indicators, explaining any result outside the range.
Frequently asked questions
Should I use the government norms for quoting?
Government construction cost norms are a good basis when working with clients that have formal procedures (companies, public agencies) and for cross-checking. For household clients, your crew's in-house norms are closer to reality. Recording the real labor hours on every project is the only way to build reliable in-house norms.
How is a take-off for a renovation different?
The site survey must be more thorough: old walls may be concrete, old boxes have to be removed, old wires have to be pulled out or abandoned, and furniture has to be covered and protected. Increase the site condition factor and the risk contingency, and state clearly in the quotation what is not included.
How often should I update unit prices?
Get fresh prices for copper wire and cable for every quotation; update switchgear prices every quarter. Quotations sent to clients always state a validity period, usually 15–30 days.
Further reading
Review how to take on jobs and quote in the lesson Quoting and taking on jobs as an electrician and cable sizing in the lesson Choosing cable sizes and circuit breakers.