The distribution board is the electrician's "calling card". The homeowner never sees the cables inside the walls, but the moment they open the board they can tell whether the electrician knows the trade: neat wiring, correct colours, labels, firmly tightened terminals, clearly separated N and PE bars; or a tangled mess of wires, stacked joints, and no way of knowing which breaker feeds what. This lesson is the combined practical exercise of Level 2: starting from the drawings, the load calculation, and the MCB, RCD and earthing system choices covered in earlier lessons, you will fully install a 12–18 module apartment distribution board.
By the end of this lesson, you will be able to:
- Choose an enclosure with the right number of modules, IP rating, material and mounting location.
- Lay out the devices in the order supply → main switch → RCD/groups → final circuits, with spare capacity.
- Wire the inside of the board with correct colours and cross-sections, neatly, and with sensible bending radii.
- Separate the N bars by RCD group, provide a common PE bar, and connect them correctly.
- Label the circuits, fix a single-line diagram in the board, and test and measure before energising.
Step 1. Choosing the enclosure and its location
- Number of modules: count the devices on the drawing (1P MCB = 1 module, 2P = 2, 2P RCCB = 2, 1P+N RCBO usually 1–2, surge protective device 2), then add about 20–30% spare space. A 2–3 bedroom apartment usually uses a 12–18 module board; a multi-storey town house has a main board plus a board on each floor.
- Flush or surface mounted: flush boards look neat, but the back box must be built in during the rough construction stage at the correct height.
- IP rating: IP30–IP40 is sufficient in dry indoor areas; for damp locations, balconies and garages choose IP55 or higher.
- Location: easy to reach, not in a bathroom, not behind a door, not above a cooker or sink; the bottom edge is usually at about 1.4–1.6 m, high enough to keep it out of reach of small children while still allowing adults to operate it. Leave clear working space in front of the board.
Photo: O.Brill / Wikimedia Commons, CC BY 2.5
Step 2. Laying out the devices
Arrange devices from left to right and top to bottom, following the flow of energy:
- 2P main circuit breaker (or an isolator plus a main breaker).
- Surge protective device (SPD) if fitted, connected directly after the main breaker, together with a breaker or fuse protecting the SPD as specified by the manufacturer (covered in detail in Level 3).
- Group not protected by a 30 mA RCD (if the design allows): lighting and the refrigerator – so that a leakage fault on a socket circuit does not plunge the home into darkness or spoil the food. Note that in a TT system every circuit needs RCD protection against indirect contact; in that case this group goes behind a 100–300 mA type S RCD, or uses individual RCBOs.
- RCD group 1: socket outlets in the rooms.
- RCD group 2: bathrooms, water heaters, washing machine.
- Air conditioners and induction hob on individual RCBOs or within a group, according to the design.
Principles: devices in the same group sit next to each other; large loads sit close to the supply to shorten the feed conductors; leave spare spaces at the end of each row.
Step 3. N and PE busbars
- N bar: each RCD has its own N bar (or its own N link). The N conductor of every final circuit belonging to an RCD must return to that RCD's N bar. This is essential to stop the RCD from nuisance tripping (see the RCD lesson).
- PE bar: a single common bar, connected to the PE conductor from the earth rod (TT) or from the floor board (TN). Every circuit PE conductor and the metal enclosure of the board are connected to this bar.
- The N bar and PE bar are insulated from each other and from the enclosure (the N bar sits on an insulated base). There is no N–PE link in an apartment board.
- Only one conductor per screw terminal (unless the bar is designed to take 2 conductors of the same cross-section).
For boards with a comb busbar feeding a row of MCBs: use a comb with the correct number of poles from the same manufacturer as the breakers, cut off the excess length and fit the end caps. A comb busbar makes supply connections quick and tidy, and carries current better than looping wires from one breaker to the next.
Step 4. Wiring inside the board
- The incoming supply cable enters from the top or bottom, following the conduit route, and connects to the main breaker.
- Outgoing circuit conductors run along trunking or are bundled neatly, with right-angle bends that have a proper radius, and never cross over the front of the devices.
- Conductor colours: phase brown/red/black according to the project convention, N blue, PE green-and-yellow. Links between devices inside the board use the same cross-section as the largest final circuit they supply.
- Flexible stranded conductors must be fitted with crimped ferrules of the correct size before going into MCB terminals. Solid conductors must be stripped to the correct length, with no bare copper showing outside the terminal.
- Tighten terminals to the torque specified by the manufacturer (typically 2–3.5 N·m for MCBs). Give every conductor a pull test.
- Bundle conductors with cable ties, but not so tight that they damage the insulation; leave enough slack to replace devices later.
Photo: Tomwsulcer / Wikimedia Commons, CC0
Warning: All board installation work is done with the supply to the board isolated, locked off, tagged and proven dead at the supply cable ends, following the Level 1 procedure. Never "hot-wire" the supply cable into the main breaker.
Step 5. Labelling and documentation in the board
- Fix a label under each breaker: the circuit number and an easy-to-understand name ("3 – Bedroom 1 sockets", "7 – Water heater, 2nd floor bathroom").
- Number the conductor ends (numbered ferrule markers) for each circuit to match the circuit number.
- Fix a reduced-size single-line diagram on the inside of the board door (see the drawing-reading lesson).
- Fix a "Danger – 220V" warning label on the outside.
- Add a note: "Press the RCD T (test) button every 3–6 months".
Photo: Dmitry G / Wikimedia Commons, CC BY-SA 3.0
Step 6. Checks before energising
- Visual inspection: no bare conductor ends, no metal swarf, no insulation trapped under terminals, and the cover plate (board front panel) fits properly.
- Re-tighten every terminal one final time.
- PE continuity: measure the resistance between the PE bar and the earth pin of each socket outlet and each appliance casing: it must be low (usually below 1Ω for domestic circuits, depending on conductor length).
- Insulation resistance of each circuit at 500V DC (next lesson): L–N, L–PE and N–PE, all ≥ 1 MΩ according to IEC 60364-6; in practice new circuits usually read hundreds of MΩ. Remember to disconnect electronic equipment, LED lamps and SPDs before testing.
- Energise: switch on the main breaker and measure the incoming voltage; switch on each group and each circuit in turn; use a voltage tester or socket tester to check the polarity of each socket (phase on the correct side, PE present).
- Test the RCDs using the T button and with a trip-time tester.
- Run under load for 30 minutes, measure terminal temperatures with an infrared thermometer and compare them. If any terminal is clearly hotter than the others: switch off and inspect it.
Tools and materials to prepare
| Category | List |
|---|---|
| Hand tools | 1000V insulated screwdrivers (flat and Phillips), 1–5 N·m torque screwdriver, automatic wire strippers, ferrule crimping pliers, side cutters, cable knife, tape measure, marker pen |
| Testing | Two-pole voltage tester, digital multimeter, insulation resistance tester, RCD tester (or multifunction installation tester), infrared thermometer |
| Materials | Enclosure, DIN rail, N bar with insulated base, PE bar, comb busbar, ferrules in various sizes, numbered ferrule markers, cable ties, printed labels, blanking covers for empty module spaces |
| Safety | Insulating gloves, safety glasses, LOTO locks and tags, warning signs |
Upgrading old boards: what you usually find
Most of a journeyman's work is not installing new boards but upgrading old ones: adding an air conditioner, adding an RCD, replacing a burnt-out breaker. Old boards in Vietnam often have the following problems:
- Changeover knife switches or porcelain fuse holders that have deteriorated; breakers of unknown brand, warped by heat.
- No RCD, no PE conductor, or the PE conductor connected to N.
- Circuit conductors joined over and over with tape, a mix of colours, and no idea which circuit is which.
- No space left: a previous electrician has fitted extra breakers "hanging" outside the board.
Upgrade procedure: (1) isolate, lock off and prove dead; (2) take photos, then trace and record every circuit by switching on one breaker at a time and checking which rooms have power; (3) test the insulation of each old circuit before connecting it to the new board – old circuits often give low readings because of damp and need to be fixed first; (4) draw up the new board layout based on the load schedule; (5) give the homeowner a quotation that includes options for adding RCDs and earthing; (6) carry out the work and test it just like a new board. Do not transfer old circuits to a new board without testing them: the new RCD will trip as soon as power is switched on if an old circuit is leaking, and the customer will think the electrician did something wrong.
Practical exercise: a 2-bedroom apartment board
| No. | Device | Circuit | Conductor | Group |
|---|---|---|---|---|
| 0 | 2P MCB C40, 6 kA | Main | 10 mm² | – |
| 1 | RCBO C10 30 mA type A | Lighting for the whole home | 1.5 mm² | Individual |
| 2 | RCBO C16 30 mA type A | Refrigerator + auxiliary kitchen sockets | 2.5 mm² | Individual |
| 3–5 | 2P RCCB 40A 30 mA type A + 3 × MCB C20 | Sockets: living room, bedroom 1, bedroom 2 | 2.5 mm² | Group 1 |
| 6–7 | 2P RCCB 40A 30 mA type A + MCB C20, C20 | Water heater, washing machine | 2.5–4 mm² | Group 2 |
| 8–9 | RCBO C16 30 mA type A × 2 | Air conditioners 1 and 2 | 2.5 mm² | Individual |
| 10 | RCBO C32 30 mA type A | Induction hob | 6 mm² | Individual |
Coordination check: the C40 main breaker is only 1.25 times the largest final circuit breaker (C32), which does not meet the 1.6 rule. Options: increase the main breaker to C50 or C63 if the meter and incoming cable allow it, or accept limited selectivity and check the manufacturer's tables. This is exactly the kind of decision a journeyman must raise with the homeowner and record in the documentation, rather than quietly installing it.
Common mistakes
| Mistake | Consequence | Correct practice |
|---|---|---|
| One common N bar for several RCDs | RCDs nuisance trip | A separate N bar for each group |
| Two conductors of different sizes in one MCB terminal | The smaller conductor works loose and overheats | One conductor per terminal, or a purpose-made twin ferrule |
| Flexible conductors without ferrules | Strands splay out, poor contact | Crimp ferrules of the correct size |
| No labels, no diagram | Repairs take longer, wrong circuit switched off | A label on every breaker, a diagram inside the door |
| No spare space left | Adding a circuit means replacing the board | Leave 20–30% of modules spare |
| Insulation testing with LED lamps and SPDs still connected | Damaged equipment, false results | Disconnect electronic equipment before testing |
Pass criteria for this lesson
- Fully install a 12–18 module board according to the drawing within 4 hours.
- 100% of terminals tightened to the correct torque and passing the pull test; no bare conductor visible outside any terminal.
- N bars correctly separated by RCD group, verified by a load test with no nuisance tripping.
- Complete circuit labels, numbered ferrule markers and a single-line diagram inside the board door.
- A pre-energisation test record: PE continuity, insulation of each circuit, polarity, RCD trip time, and terminal temperatures after 30 minutes.
Frequently asked questions
Should I use a plastic or a metal enclosure?
Plastic enclosures insulate well, are light, do not need the enclosure connected to PE, and are common in apartments. Metal enclosures are stronger and more impact-resistant, and are used for main boards, garages and workshops; the enclosure and door must be connected to PE with a flexible conductor.
Should every circuit have an RCBO?
If the budget allows, that is the best option for reliability. If not, splitting the circuits into 2–3 RCCB groups is a balanced solution.
Does the board need a surge protective device?
It is advisable in areas with frequent thunderstorms, in homes with a lot of expensive electronic equipment, and in homes with solar power. Level 3 covers how to choose and install SPDs.