"All done, I switched it on and everything lights up" is not commissioning. Commissioning means proving with measured data that the electrical installation you have just completed is safe and built to the design, and then recording it in a signed report. The test report is what separates a professional journeyman from a casual hired hand: it protects the homeowner, it protects you if something goes wrong later, and it is the baseline document for every future maintenance visit. This is the final lesson of Level 2: every measurement you have learned is brought together into one complete initial verification procedure according to IEC 60364-6 (TCVN 7447-6).
By the end of this lesson, you will be able to:
- Carry out a visual inspection using a checklist before testing.
- Perform the tests in the correct order: PE continuity, insulation, polarity, earth fault loop impedance, RCD, earth resistance, functional checks.
- Assess pass/fail against limit values.
- Complete the test report and the handover documentation package for the homeowner.
- Show the homeowner how to operate and carry out basic maintenance on the installation.
Why the order of testing matters
IEC 60364-6 requires the tests to be carried out in a logical sequence, and if a test fails, the fault must be corrected and that test repeated, together with any earlier tests that may have been affected. The logic is simple: the dead tests come first to make sure it is safe to energise; the live tests come afterwards. You cannot safely measure earth fault loop impedance unless you are sure the PE conductor is continuous.
Step 1. Visual inspection
Done before energising, using a checklist. Example of a short checklist for a home:
| Item | What to check |
|---|---|
| Distribution board | Devices match the drawing (curve, In, IΔn, RCD type); terminals tightened; separate N bar per group; circuit labels; diagram inside the door; front cover fully closed |
| Conductors | Correct cross-section and colour; no bare conductors; conduits and junction boxes covered; cables passing over sharp edges are protected |
| Accessories and equipment | Sockets have PE; switches break the phase conductor; equipment has the right IP rating for its zone (bathroom, outdoors) |
| Earthing | Earth rods, inspection pit, main earthing conductor, equipotential bonding of water pipes, gas pipes and metal frames |
| Protection | 30 mA RCD for sockets, bathrooms, water heaters and outdoor circuits; SPD if included in the design |
| Clearances | Board easy to access; sockets at the required distance from taps and sinks according to the safety zones |
Step 2. Continuity of the PE protective conductor
Measure the resistance between the PE bar in the board and the PE terminal of each socket outlet, the metal casing of each fixed appliance, and each metal light fitting. Use a continuity range with a test current of at least 200 mA (installation testers have this function built in; ordinary multimeters do not supply enough current). Subtract the resistance of the test leads (null the leads). The result must be low and consistent with the conductor length: a 2.5 mm² conductor has about 7.4 mΩ/m, so 25 m of PE conductor ≈ 0.19Ω. An unusually high value is a sign of a loose connection or a broken PE conductor.
Ring final circuits, common in some countries, have their own specific test; homes in Vietnam mostly use radial circuits, so you will rarely come across them.
Step 3. Insulation resistance
As in the previous lesson: 500V DC, ≥ 1 MΩ for each circuit, with electronic equipment disconnected before testing. Record the L–PE, N–PE (or L+N–PE) and L–N values for each circuit.
Step 4. Polarity
Check that every switch, every 1P breaker and every Edison screw lamp holder breaks the phase conductor, and that sockets have the phase connected in the conventional position. Check by continuity testing before energising, or with a socket tester after energising. Wrong polarity means the switch breaks the N conductor: the light goes off but the lamp holder is still live, which is dangerous when changing a lamp.
Photo: Skatebiker / Wikimedia Commons, CC0
Step 5. Energising and earth fault loop impedance
Once steps 1–4 have passed, energise the installation. Measure the incoming voltage and check that every circuit is live.
Earth fault loop impedance Zs is the total impedance of the path taken by the fault current when a phase conductor touches a casing: from the source through the phase conductor to the fault point, back through the PE conductor (and the ground in a TT system) to the source. The lower Zs is, the larger the fault current, and the faster the breaker trips. A multifunction tester measures Zs at the furthest socket of each circuit.
- TN system: the condition for the MCB to disconnect within 0.4 s is Zs × Ia ≤ U0, where Ia is the instantaneous tripping current of the MCB. Example: a C20 has Ia = 10 × 20 = 200A, U0 = 230V: maximum Zs ≈ 1.15Ω (in practice use the table of maximum values corrected for conductor temperature, usually about 80% of the calculated value, i.e. ≈ 0.92Ω).
- TT system: a high Zs (tens of ohms) is normal; protection relies on the RCD with the condition RA × IΔn ≤ 50V.
Photo: Santeri Viinamäki / Wikimedia Commons, CC BY-SA 4.0
The tester also displays the prospective short-circuit current (PSCC/PFC) at the board: compare it with the breaking capacity Icn of the breakers (see the MCB lesson). If the prospective short-circuit current exceeds Icn, the breaker cannot safely interrupt the fault.
Step 6. RCD testing
At each RCD (or at a socket downstream of the RCD), use the tester:
| Test | Required result (general-type RCD) |
|---|---|
| Test current 0.5 × IΔn | Must not trip |
| Test current 1 × IΔn | Trips within ≤ 300 ms |
| Test current 5 × IΔn | Trips within ≤ 40 ms |
| Ramp test | Tripping current between 50–100% of IΔn |
| T test button | Trips when pressed |
Type S (selective) RCDs have longer trip times under their own specific requirements. Test on both half-cycles (0° and 180°) and record the higher value.
Step 7. Earth resistance and functional checks
Measure the earth rod resistance using the 3-pole method (see the earthing lesson) and record the weather conditions. Then carry out functional checks: every switch, two-way switch, light, socket and fixed appliance works correctly; breakers switch on and off smoothly; run under load and measure the board terminal temperatures after 30 minutes.
The test report
As a minimum, the report includes:
- General information: project, address, homeowner, installation contractor, person testing, test date, weather.
- Supply characteristics: earthing system (TT/TN-C-S), measured voltage, prospective short-circuit current, earth resistance.
- Test instruments: name, serial number, date of last calibration.
- Results table for each circuit: circuit number, name, protective device (type, In, curve), conductors (phase/PE), PE continuity, insulation, polarity, Zs, RCD (trip times at 1× and 5×).
- Visual inspection results: checklist marked pass/fail.
- Outstanding issues and recommendations.
- Conclusion: pass / fail / conditional pass; signatures of the tester and the homeowner.
Handover documentation for the homeowner
- As-built drawings: floor plan with the actual cable routes (especially cable positions in walls and floors), and the single-line diagram of the board.
- The test report and photos of the cable routes taken before plastering (extremely valuable when drilling into walls later).
- List of main materials: brand and model of breakers, RCDs, cables; warranty cards.
- Instructions: press the RCD T button regularly; what to do when a breaker or RCD trips; never replace a breaker with a larger one yourself; when to call an electrician.
- Recommended periodic inspection schedule: for homes, a full inspection every 5–10 years, as recommended in many countries; sooner for rented properties, after major alterations, or after flooding.
Photo: Charanjitmannu / Wikimedia Commons, CC BY-SA 4.0
What to do when a result fails
Commissioning is not about "letting it through". When a value fails, the journeyman follows this principle: stop, find the cause, correct it, test again, and record both the before and after values in the report.
| Failed result | Common cause | Remedy |
|---|---|---|
| Unusually high PE continuity reading | Loose PE screw in a socket, PE conductor broken in a junction box | Check from the socket back towards the board and re-tighten |
| Insulation < 1 MΩ | Appliances left plugged in; cable damaged during pulling; damp junction box | Unplug appliances, split sections to find the leakage (previous lesson) |
| Zs above the maximum value (TN) | Long run, small cross-section, poor joints | Increase the cross-section, reduce In, change to a B curve, or rely on an RCD |
| RCD trips slowly or not at all | Faulty RCD; wrong connections; unsuitable RCD type | Check connections, replace the RCD, test again |
| RCD trips at 0.5 × IΔn | High standing leakage on the group; RCD too sensitive | Measure standing leakage, regroup the circuits |
| PSCC above the breaker's Icn | Close to the transformer substation | Fit breakers with a higher Icn, or provide upstream back-up protection according to the manufacturer's tables |
When an item cannot be corrected immediately (for example, the homeowner needs to approve the cost of replacing the main breaker), record it clearly under "Outstanding issues and recommendations" and conclude "conditional pass" or "fail" – never write "pass" just to get it done. An honest report protects you better than a pretty one.
Level 2 final practical exercise
On an apartment simulation board with 8 circuits, the instructor sets up 3 hidden faults (for example: one socket with L–N reversed, one circuit with its N connected to another group's N bar, one circuit with a loose PE). The trainee:
- Carries out the visual inspection and fills in the checklist.
- Performs all the tests in the correct order and fills in the report.
- Finds all 3 faults, narrows them down, corrects them and tests again.
- Completes the report and explains the results to the "homeowner" within 5 minutes.
Completing this lesson together with the end-of-module quiz is the requirement for receiving the Level 2 – Journeyman Electrician certificate on NAMBIN.
Common mistakes
| Mistake | Consequence | Correct practice |
|---|---|---|
| Energising before testing PE continuity and insulation | Risk of live casings, short circuit on switch-on | Dead tests first, live tests afterwards |
| Testing RCDs only with the T button | The actual trip time is unknown | Test with an instrument at 1× and 5× IΔn |
| Not measuring Zs at the furthest point | A circuit that cannot disconnect in time goes unnoticed | Measure at the furthest socket or appliance on each circuit |
| Report missing test instrument details | The report carries less legal weight | Record model, serial number, calibration date |
| No photos of cable routes before plastering | Cables drilled into during later repairs | Photograph, measure positions, include in the documentation |
Pass criteria for this lesson
- Complete all 7 steps in the correct order on the simulation board, without skipping any step.
- Find 3 out of 3 hidden faults, correct them and confirm by retesting.
- A report with all 7 sections, every value with its unit, and a clear conclusion.
- Correctly calculate the maximum Zs for 3 MCB types (B16, C16, C20) in a TN system.
- Hand over the documentation and give the homeowner all 4 operating instructions.
Frequently asked questions
Can I commission an installation without a multifunction tester?
Part of it can be done with an insulation tester, a multimeter with a high-current continuity range and a separate RCD tester. But to measure Zs and RCD trip times accurately, a multifunction tester is the professional tool worth investing in once you take on complete projects. Many electricians rent one or share one within their team.
Does the test report have legal value?
A report signed by both parties is a document recording the condition of the installation at the time of handover. On contracted projects, the commissioning report is the basis for payment and warranty. Level 4 covers contracts, warranties and as-built documentation in depth.
Do I need to test again when I only add one socket?
Yes, at least for the circuit that was altered: PE continuity, insulation, polarity, Zs at the new socket, and a test of the RCD protecting that circuit. Fill in a short report for the alteration work.